File #: 19-0258    Version: 1 Name: A RESOLUTION APPROVING HERITAGE PARK GAZABO STEP REDESIGN PROJECT
Type: Resolution Status: Adopted
File created: 4/29/2019 In control:
On agenda: 7/1/2019 Final action: 7/1/2019
Title: A RESOLUTION APPROVING HERITAGE PARK GAZEBO STEP REDESIGN PROJECT
Attachments: 1. Capital Project Worksheet Gazebo Steps, 2. Gazebo Step Plans
Title
A RESOLUTION APPROVING HERITAGE PARK GAZEBO STEP REDESIGN PROJECT

Summary
Description of Topic: (who, what, where, when, why and how much)
The brick steps at the Heritage Park Gazebo need to ne reconstructed to extend across the entire south side. This will allow the gazebo serve as a stage for events. We will add a concrete landing for the steps and remove the railings on each side to allow for better veiwing of events.

Budgetary Impact:
Non-Capital Item:
____ Budgeted under account #_______________ (discussion item)
____ Not budgeted, requesting transfer of $__________ from Account #______________ to Account #_____________.**Request to Transfer Departmental Budget Dollars form must be attached**
____ Not budgeted requiring increase to account #___________ in the amount of $____________.**Request to Increase Departmental Budget Dollars form must be attached**

Capital - Departmental **Capital Purchase Worksheet form must be attached**
____ Budgeted under account #______________ for $_________ and described in budget as ________________________. Additional amount needed, if any: Increase in budget of $_________ OR, transfer of $________ from Account #____________ to Account #_____________**Request to Increase OR Request toTransfer Departmental Budget Dollars form must be attached**
____ Not Budgeted - account #____________ requires budget increase of $_____________.**Request to Increase Departmental Budget Dollars form must be attached**

Capital Project - **If requesting to start a project, a Capital Project Worksheet form must be attached**
In current year Capital Projects Plan:
__x__ Yes, described as Heritage Park Gazabo Step Redesign, planned amount $30,000, requesting $30,000.00 as total project estimate, including contingencies, under account #400-3020-5145 Heritage Park Gazebo Steps
_____ No, requesting $___________ as total project estimate, including contingencies, under account #...

Click here for full text