File #: 24-0260    Version: 1 Name: A Resolution Appropriating Funds and Approving Sawgrass Consulting, LLC for remaining Parking Lot & Road Construction north of CAFFM Adjacent to the New Pickleball Courts.
Type: Resolution Status: Agenda Ready
File created: 4/8/2024 In control: City Council
On agenda: 4/15/2024 Final action: 4/15/2024
Title: A Resolution Appropriating Funds and Approving Sawgrass Consulting, LLC for remaining Parking Lot & Road Construction north of CAFFM Adjacent to the New Pickleball Courts.
Attachments: 1. Road Work Figures - 04-08-2024, 2. Pickleball Road - Trawick Signature, 3. Pickleball Road and Pickleball Courts- MThompson Signature, 4. PIckleball Road - Sawgrass, 5. Sawgrass Pickleball Complex & Parking Proposal
Title
A Resolution Appropriating Funds and Approving Sawgrass Consulting, LLC for remaining Parking Lot & Road Construction north of CAFFM Adjacent to the New Pickleball Courts.

Summary
The Leisure Services Division previously appropriated $84,000 in Resolution 23-0244 for the purpose of the Street Department to build the road base for the new pickleball road. During the road construction, the Street Department has spent $118,321.85. Due to the added drainage boxes, grates, piping, pond size increase/outfall and additional parking. Additional cost also included the machine rentals needed to complete the complexity of the grade. We would like to request that these additional expenditures be memorialized and increase the account 400-5030-5108 Pickleball Road Addition by $ $34,321.85. The Leisure Services Division is requesting to appropriate an additional $334,200 to this project which includes $51,400 for Sawgrass Consulting, LLC professional services contract and $282,300 which is estimated for this phase of the project plus $500 advertising expense.


Capital Project - **If requesting to start a project, a Capital Project Worksheet form must be attached**
In current year Capital Projects Plan:
__X__ Yes, described as _Pickleball Road Addition. We are requesting an increase of $368,521.85 under account #400-5030-5108
_____ No, requesting $___________ as total project estimate, including contingencies, under account #____________________.
_____ No, requesting an increase of $___________ to an already approved project titled ________________________ that is being tracked under Account No. ___________________.

Body
WHEREAS, Resolution 23-0244 appropriated $84,000 for Public Works to construct the Pickelball road, and,
WHEREAS, the cost for Public Works to construct the road was $118,321.85, which exceeded the budgeted amount by $34,321.85, and,
WHEREAS, Sawgrass Consulting, LLC has provided a proposal f...