File #: 19-0252    Version: 1 Name: A RESOLUTION APPROVING AZALEA AVENUE DRAINAGE IMPROVEMENTS
Type: Resolution Status: Adopted
File created: 4/25/2019 In control:
On agenda: 5/9/2019 Final action: 5/9/2019
Title: A RESOLUTION APPROVING AZALEA AVENUE DRAINAGE IMPROVEMENTS
Attachments: 1. Capital Project Worksheet

Title

A RESOLUTION APPROVING AZALEA AVENUE DRAINAGE IMPROVEMENTS

 

Summary

Description of Topic: (who, what, where, when, why and how much)

There is standing water along the southwest corner of the Intersection of East Azalea Avenue and S Pecan Street along the existing sidewalks. Public Works Department has reviewed the planned improvements to construct a concrete calley gutter across Azalea Avenue and is scheduled to complete the project.

 

Budgetary Impact:

   Non-Capital Item:

      ____ Budgeted under account #_______________ (discussion item)

      ____ Not budgeted, requesting transfer of $__________ from Account #______________ to Account #_____________.**Request to Transfer Departmental Budget Dollars form must be attached**

      ____ Not budgeted requiring increase to account #___________ in the amount of $____________.**Request to Increase Departmental Budget Dollars form must be attached**

 

   Capital - Departmental **Capital Purchase Worksheet form must be attached**

      ____ Budgeted under account #______________ for $_________ and described in budget as ________________________. Additional amount needed, if any: Increase in budget of  $_________ OR, transfer of $________ from Account #____________ to Account #_____________**Request to Increase OR Request toTransfer Departmental Budget Dollars form must be attached**

      ____ Not Budgeted - account #____________ requires budget increase of $_____________.**Request to Increase Departmental Budget Dollars form must be attached**

 

   Capital Project - **If requesting to start a project, a Capital Project Worksheet form must be attached**

      In current year Capital Projects Plan: 

        __X__ Yes, described as Azalea Avenue Drainage Improvements, planned amount $7,500, requesting $7,500 as total project estimate, including contingencies, under account #400-3020-5102 A19 Azalea Drainage Improvements.

        _____ No, requesting $___________ as total project estimate, including contingencies, under account #____________________.

        _____ No, requesting an increase of $___________ to an already approved project titled ________________________ that is being tracked under Account No. ___________________.

 

Body

 

     WHEREAS,  There is standing water along the southwest corner of the Intersection of East Azalea Avenue and S Pecan Street along the existing sidewalks, and

 

     WHEREAS,   Public Works Department has reviewed the planned improvements to construct a concrete valley gutter across Azalea Avenue and is scheduled to complete the project.

 

     NOW THEREFORE BE IT RESOLVED that the City Council of the City of Foley, Alabama, as follows:

 

     SECTION 1:  Approves the Azalea Avenue Drainage Improvement Project, to be completed by Public Works Department, and appropriates up to $7,500 under Account No. 400-3020-5102 A19 Azalea Drainage Improvements.

    

     SECTION 2:  This Resolution shall become effective immediately upon its adoption as required by law.