File #: 17-0066    Version: 1 Name: Crown Walk Dr. Drainage Improvements Project
Type: Resolution Status: Adopted
File created: 1/30/2017 In control:
On agenda: 2/6/2017 Final action: 2/6/2017
Title: Crown Walk Dr. Drainage Improvements Project
Attachments: 1. Signed Crown Walk Drg. Imps. Pre-Project Checklist
Title
Crown Walk Dr. Drainage Improvements Project

Summary
Description of Topic: (who, what, where, when, why and how much)
Request approval of project and appropriation of funds for Crown Walk Dr. drainage improvements.

Budgetary Impact:
Non-Capital Item:
____ Budgeted under account #_______________ (discussion item)
____ Not budgeted, requesting transfer of $__________ from Account #______________ to Account #_____________.
____ Not budgeted requiring increase to account #___________ in the amount of $____________.

Capital - Departmental
____ Budgeted under account #______________ for $___________ and described in budget as __________________________________.
Additional amount needed, if any: Increase in budget of $_____________ OR, transfer of $___________ from Account #____________ to Account #_______________
____ Not Budgeted - account #____________ requires budget increase of $_____________.

Capital Project - **THE PRE-PROJECT CHECKLIST AND BUDGET CHECKLIST MUST BE ATTACHED TO THIS FILE**
In current year Capital Projects Plan:
_____ Yes, planned amount $___________, requesting $_________ as total project estimate, including contingencies, under account #_________________
__X__ No, requesting $150,000______ as total project estimate, including contingencies, under account #12-665-7128 A19 CROWN___________

Body

WHEREAS, there is a need for drainage improvements along Crown Walk Drive to alleviate flooding during rain storms, and
WHEREAS, the Engineering Department will design a plan to repair the drainage issues and the construction work will be publicly bid, and
WHEREAS, the cost estimate for the drainage improvements is $150,000.00

NOW THEREFORE BE IT RESOLVED that the City Council of the City of Foley, Alabama, as follows:

SECTION 1: Approves the project to be designed by the Engineering Department and the construction work to be pub...