File #: 15-0620    Version: 1 Name: Change Order for Interpretive Center
Type: Resolution Status: Adopted
File created: 10/9/2015 In control: Community Development Deptartment
On agenda: 10/19/2015 Final action: 10/19/2015
Title: Request change order for Graham Creek Interpretive Center to add Alternatives 1 and 2
Attachments: 1. RFP #02 Site Concrete
Related files: 15-0224, 15-0096, 15-0310
Title
Request change order for Graham Creek Interpretive Center to add Alternatives 1 and 2

Summary
Description of Topic: (who, what, where, when, why and how much)
Request a change order to add alternatives 1 and 2 to the Graham Creek Interpretive Center with existing funding from Resolution 15-2173 at a cost of $53,365.00.

Budgetary Impact:
Non-Capital Item:
____ Budgeted under account #_______________ (discussion item)
____ Not budgeted, requesting transfer of $__________ from Account #______________ to Account #_____________.
____ Not budgeted requiring increase to account #___________ in the amount of $____________.

Capital - Departmental
____ Budgeted under account #______________ for $___________ and described in budget as __________________________________.
Additional amount needed, if any: Increase in budget of $_____________ OR, transfer of $___________ from Account #____________ to Account #_______________
____ Not Budgeted - account #____________ requires budget increase of $_____________.

Capital Project - **THE PRE-PROJECT CHECKLIST AND BUDGET CHECKLIST MUST BE ATTACHED TO THIS FILE**
In current year Capital Projects Plan:
___X__ Yes, planned amount $_1,345,449.45_, requesting $__No additional funds_______ as total project estimate, including contingencies, under account #12-665-7342 R18
_____ No, requesting $___________ as total project estimate, including contingencies, under account #____________________

Body

WHEREAS, Youngblood Barrett Construction submitted alternates 1 and 2 which were not accepted with the original contract, and
WHEREAS, the City allocated $220,449.45 under Resolution 15-2173 for the City staff to construct the parking areas and ancillary roadways, and
WHEREAS, ribbon curbing, sidewalks and disability parking are needed to be installed, and
WHEREAS, Youngblood Barrett Construction alternates 1 and 2 can be adde...