File #: 24-0458    Version: 1 Name: Transfer for Capital Project
Type: Resolution Status: Adopted
File created: 7/29/2024 In control:
On agenda: 8/5/2024 Final action: 8/5/2024
Title: A Resolution to Transfer Funds from Operations to the Beulah Heights Park Capital Project.
Attachments: 1. Jeff-Lee-Parks-Recreation
Title
A Resolution to Transfer Funds from Operations to the Beulah Heights Park Capital Project.

Summary
The Parks and Recreation Department is requesting to transfer $15,000 from the Mel Roberts Park Maintenance Operations Account to the Beulah Heights Park Upgrades Capital Project. We did not anticipate having to install a grinder pump as well as the much higher cost of sidewalks to make the new bathroom building ADA compliant.

Budgetary Impact:
Non-Capital Item:
____ Budgeted under account #_______________ (discussion item)
____ Not budgeted, requesting transfer of $__________ from Account #______________ to Account #_____________.**Request to Transfer Departmental Budget Dollars form must be attached**
____ Not budgeted requiring increase to account #___________ in the amount of $____________.**Request to Increase Departmental Budget Dollars form must be attached**

Capital - Departmental **Capital Purchase Worksheet form must be attached**
____ Budgeted under account #______________ for $_________ and described in budget as ________________________. Additional amount needed, if any: Increase in budget of $_________ OR, transfer of $________ from Account #____________ to Account #_____________**Request to Increase OR Request toTransfer Departmental Budget Dollars form must be attached**
____ Not Budgeted - account #____________ requires budget increase of $_____________.**Request to Increase Departmental Budget Dollars form must be attached**

Capital Project - **If requesting to start a project, a Capital Project Worksheet form must be attached**
In current year Capital Projects Plan:
_____ Yes, described as __________________________, planned amount $___________, requesting $_________ as total project estimate, including contingencies, under account #_________________
_____ No, requesting $___________ as total project estimate, including contingencies, under account #____________________....

Click here for full text