File #: 17-0301    Version: 1 Name: Amend Volkert, Inc.'s CE&I Contract for TIGER Phases I and II
Type: Resolution Status: Adopted
File created: 5/18/2017 In control:
On agenda: 6/19/2017 Final action: 6/19/2017
Title: Amend Volkert, Inc.'s CE&I Contract for TIGER Phases I and II
Attachments: 1. TIGER I&II Labor Detail
Title
Amend Volkert, Inc.'s CE&I Contract for TIGER Phases I and II

Summary
Description of Topic: (who, what, where, when, why and how much)
Consider amending Volkert, Inc.'s CE&I contract to account for paying 75% of the liquidated damages amounts for TIGER Phases I and II.

Budgetary Impact:
Non-Capital Item:
____ Budgeted under account #_______________ (discussion item)
____ Not budgeted, requesting transfer of $__________ from Account #______________ to Account #_____________.
____ Not budgeted requiring increase to account #___________ in the amount of $____________.

Capital - Departmental
____ Budgeted under account #______________ for $___________ and described in budget as __________________________________.
Additional amount needed, if any: Increase in budget of $_____________ OR, transfer of $___________ from Account #____________ to Account #_______________
____ Not Budgeted - account #____________ requires budget increase of $_____________.

Capital Project - **THE PRE-PROJECT CHECKLIST AND BUDGET CHECKLIST MUST BE ATTACHED TO THIS FILE**
In current year Capital Projects Plan:
_____ Yes, planned amount $___________, requesting $_________ as total project estimate, including contingencies, under account #_________________
_____ No, requesting $___________ as total project estimate, including contingencies, under account #____________________

Body

WHEREAS, TIGER Phases I and II projects had liquidated damage payments from the contractors, and

WHEREAS, ALDOT stated the liquidated damages are to be paid to Volkert, Inc., the engineering consultant for the projects, and

WHEREAS, 75% of the liquidated damage payments are to be paid to Volkert, Inc. for their unbilled man hours as they continued to oversee the construction after the CE&I fund was depleted.

NOW THEREFORE BE IT RESOLVED that the City Council of the City of Foley, Alabama, as follo...

Click here for full text