Acceptance of Volkert Supplemental Agreement No. 8 to Accomplish the Construction of a Fuel Farm at the Foley Municipal Airport and Approval to Bid Project
Summary
DESCRIPTION OF TOPIC: (who, what, when, where, why, and how much)
Acceptance of Volkert Supplemental Agreement No. 8 for professional services in the amount of $55,232.24 to accomplish the construction of a fuel farm at the Foley Municipal Airport and approval to bid this project.
SOURCE OF FUNDING:
Please provide the amount requested: $55,232.24
Is this a budgeted item? No
Please provide the budgeted amount: $_____0________ Account No. __12-665-7323, R01, VLKSA8
If budgeted, is this a capital purchase, capital project, or special fund? _________________________
Was this item included in the Fiscal Year Capital Projects Plan? No
If yes, please provide the amount included in Capital Projects Plan: $___________
Body
WHEREAS, the Alabama Department of Environmental Management (ADEM) has determined that the underground fuel storage tank at the Foley Municipal Airport requires closure and removal as per Resolution 13-0232, and,
WHEREAS, Resolution 13-0232 has approved using Volkert Engineering under Professional Services contract dated April 22, 2010 to develop and design the specifications in preparation to bid this project.
NOW THEREFORE BE IT RESOLVED that the City Council of the City of Foley, Alabama, as follows:
SECTION 1: Accepts Supplemental Agreement No. 8 as prepared by Volkert, Inc. for professional services in the amount of $55,232.24 to accomplish the construction of a fuel farm at the Foley Municipal Airport and amends 12-665-7323, R01, VLKSA8, and;
SECTION 2: Approves going to bid for the construction of a fuel farm at the Foley Municipal Airport.
SECTION 3: This Resolution shall become effective immediately upon its adoption as required by law.