File #: 23-0043    Version: 1 Name: A Resolution Approving Engineering Design Group's Professional Services Proposal for Replacement Pipe on County Road 12.
Type: Resolution Status: Adopted
File created: 2/6/2023 In control:
On agenda: 2/6/2023 Final action: 2/6/2023
Title: A Resolution Approving Engineering Design Group's Professional Services Proposal for Replacement Pipe on County Road 12.
Attachments: 1. EDG Proposal, 2. Budget Increase Capital Projects, 3. City of Foley Mail - CR12 Approval
Title
A Resolution Approving Engineering Design Group's Professional Services Proposal for Replacement Pipe on County Road 12.

Summary
Public Works and Engineering recommend the immediate replacement of the failing corrugated pipe on County Road 12 near Cottages on the Greens Subdivision and request to begin the project

Budgetary Impact:
Non-Capital Item:
____ Budgeted under account #_______________ (discussion item)
____ Not budgeted, requesting transfer of $__________ from Account #______________ to Account #_____________.**Request to Transfer Departmental Budget Dollars form must be attached**
____ Not budgeted requiring increase to account #___________ in the amount of $____________.**Request to Increase Departmental Budget Dollars form must be attached**

Capital - Departmental **Capital Purchase Worksheet form must be attached**
____ Budgeted under account #______________ for $_________ and described in budget as ________________________. Additional amount needed, if any: Increase in budget of $_________ OR, transfer of $________ from Account #____________ to Account #_____________**Request to Increase OR Request toTransfer Departmental Budget Dollars form must be attached**
____ Not Budgeted - account # requires budget increase of $.**Request to Increase Departmental Budget Dollars form must be attached**

Capital Project - **If requesting to start a project, a Capital Project Worksheet form must be attached**
In current year Capital Projects Plan:
_____ Yes, described as __________________________, planned amount $___________, requesting $_________ as total project estimate, including contingencies, under account #_________________
_X____ No, requesting $10,000.00 as total project estimate, including contingencies, under account #400-3020-5169 CR12 Storm Drain Replacement.
_____ Yes, requesting an increase of $___________ to an already approved project titled ____________________...