Title
A Resolution Approving Cunningham Delaney's Change Order No. 2 for Pine Street Drainage Improvement Project
Summary
Description of Topic: (who, what, where, when, why and how much)
Res. 18-1259 approved CO #1 to run electrical conduit from pole to building and lower 10" water main below the ditch, lower existing 8" main to backflow, add testing of 6" main and 1o" relocated main. Cunningham Delaney has submitted CO #2 in the amount of $22,975.00 to relocate the existing 10" water main and additional materials needed are: 40 LF 10" DI Pipe, (1) 10" DI 90 Bend, 180 LF 10" C900 PVC, (1) 10" DI 45 Bend, (1) 10" DI 22.5 Bend and (2) 10" Tapping Sleeve & Valve assemblies.
Budgetary Impact:
Non-Capital Item:
____ Budgeted under account #_______________ (discussion item)
____ Not budgeted, requesting transfer of $__________ from Account #______________ to Account #_____________.**Request to Transfer Departmental Budget Dollars form must be attached**
____ Not budgeted requiring increase to account #___________ in the amount of $____________.**Request to Increase Departmental Budget Dollars form must be attached**
Capital - Departmental **Capital Purchase Worksheet form must be attached**
____ Budgeted under account #______________ for $_________ and described in budget as ________________________. Additional amount needed, if any: Increase in budget of $_________ OR, transfer of $________ from Account #____________ to Account #_____________**Request to Increase OR Request toTransfer Departmental Budget Dollars form must be attached**
____ Not Budgeted - account #____________ requires budget increase of $_____________.**Request to Increase Departmental Budget Dollars form must be attached**
Capital Project - **If requesting to start a project, a Capital Project Worksheet form must be attached**
In current year Capital Projects Plan:
__X__ Yes, described as S. Pine St. Drainage Improvement, planned amount $6...