Consider approving the Myrtle Avenue valley gutter repair project and R&S Paving and Grading, Inc.'s proposal to perform the repairs.
Budgetary Impact:
Non-Capital Item:
____ Budgeted under account #_______________ (discussion item)
____ Not budgeted, requesting transfer of $__________ from Account #______________ to Account #_____________.
__x_ Not budgeted requiring increase to account #12-600-9375_______ in the amount of $____________.
Capital - Departmental
____ Budgeted under account #______________ for $___________ and described in budget as __________________________________.
Additional amount needed, if any: Increase in budget of $_____________ OR, transfer of $___________ from Account #____________ to Account #_______________
____ Not Budgeted - account #____________ requires budget increase of $_____________.
Capital Project - **THE PRE-PROJECT CHECKLIST AND BUDGET CHECKLIST MUST BE ATTACHED TO THIS FILE**
In current year Capital Projects Plan:
_____ Yes, planned amount $___________, requesting $_________ as total project estimate, including contingencies, under account #_________________
_____ No, requesting $___________ as total project estimate, including contingencies, under account #____________________
Body
WHEREAS, there is a need to repair the valley gutters on East and West Myrtle Avenue, and
WHEREAS, R&S Paving and Grading, Inc. has submitted a proposal to perform the work, and
WHEREAS, an increase in funds is needed to perform work related to this project.
NOW THEREFORE BE IT RESOLVED that the City Council of the City of Foley, Alabama, as follows:
SECTION 1: Approves appropriation of $8,000 to Account No. 12-600-9375.
SECTION 2: Approves the Myrtle Avenue valley gutter repairs and R&S Paving and ...