File #: 14-0463    Version: 1 Name: Amend Resolution for Pecan Street Permanent Repairs
Type: Resolution Status: Adopted
File created: 6/30/2014 In control:
On agenda: 7/7/2014 Final action: 7/7/2014
Title: Amend Resolution for Pecan Street Permanent Repairs
Attachments: 1. Pecan St. Perm. Repairs
Related files: 14-0345
Title
Amend Resolution for Pecan Street Permanent Repairs
 
Summary
DESCRIPTION OF TOPIC: (who, what, when, where, why, and how much)
Amend Resolution No. 14-0190 to clarify Volkert, Inc.'s contract amount and approve contract for Pecan Street Permanent Repairs.
 
 
SOURCE OF FUNDING:
Please provide the amount requested: $85,808
Is this a budgeted item? No      
Please provide the budgeted amount: $              Account No. 01-660-8300
If budgeted, is this a capital purchase, capital project, or special fund?      _________________________  
Was this item included in the Fiscal Year Capital Projects Plan?   No
If yes, please provide the amount included in Capital Projects Plan: $___________
 
 
Body
 
WHEREAS, due to the record rain event of April 29, 2014, FEMA Event #4176-DR-AL, there is a need for repairs to Pecan Street, and
WHEREAS, Resolution No. 14-0190 approved Volkert, Inc. to perform engineering services associated with the Pecan Street repairs in the amount of $412,500, and
WHEREAS, said amount included the construction cost which should have been omitted, making Volkert, Inc.'s total contract price to be $85,808.
NOW THEREFORE BE IT RESOLVED that the City Council of the City of Foley, Alabama, as follows:
SECTION 1:       Amends Resolution No. 14-0190 and approves Volkert, Inc.'s contract in the amount of $85,808, amending Account No. 01-660-8300 accordingly.
SECTION 2:      This Resolution shall become effective immediately upon its adoption as required by law.