Title
Approve Volkert's Change Order #1 for CDBG Project No. LR-CM-PF-12-007
Summary
DESCRIPTION OF TOPIC: (who, what, when, where, why, and how much)
Approve Volkert's recommendation of Change Order #1 with Suncoast Infrastructure, Inc. for CDBG Project No. LR-CM-PF-12-007 for $58,176
SOURCE OF FUNDING:
Please provide the amount requested: __$58,176__________
Is this a budgeted item? Yes
Please provide the budgeted amount: $_1,010,700____________ Account No. 29-600-7300 Grant Funds ($400,000) & 29-600-7305 Local Match ($610,700)__________________________
If budgeted, is this a capital purchase, capital project, or special fund? capital project___
Was this item included in the Fiscal Year Capital Projects Plan? Yes
If yes, please provide the amount included in Capital Projects Plan: $_1,060,700__________
Body
WHEREAS, the City Council awarded the construction contract for the City's 2012 CDBG Aaronville Sewer Rehab Project to Suncoast Infrastructure, Inc. in the amount of $932,845.00 to be paid for with grant funds and matching local funds from Riviera Utilities on June 3, 2013, and
WHEREAS, Volkert has recommended a change order #1 with Suncoast Infrastructure, Inc. for an additive amount of $58,176.00 for additional work not included in the original scope of work, that has been approved by ADECA and will be paid with grant funds and Riviera's local match, and
WHEREAS, the new project cost is $991,021.00 which is $19,679.00 under the project budget of $1,010,700.
NOW THEREFORE BE IT RESOLVED that the City Council of the City of Foley, Alabama, as follows:
SECTION 1: Approves Volkert's Change Order #1 with Suncoast Infrastructure, Inc. in the amount of $58,176.00.
SECTION 2: This Resolution shall become effective immediately upon its adoption as required by law.