Title
Approve E-J Builders Inc. Change Order #2 for Glenlakes Bike Path Phase II
Summary
DESCRIPTION OF TOPIC: (who, what, when, where, why, and how much)
Approve E-J Builders Inc. Change Order #2 for Glenlakes Bike Path Phase II in the amount of $1,532.40.
SOURCE OF FUNDING:
Please provide the amount requested: _$1,532.40___________
Is this a budgeted item? Yes
Please provide the budgeted amount: $_129,553,00______ Account No. _12-665-7281 Q64 CONST____
If budgeted, is this a capital purchase, capital project, or special fund? Capital Project
Was this item included in the Fiscal Year Capital Projects Plan? Yes/No
If yes, please provide the amount included in Capital Projects Plan: $___________
Body
WHEREAS, the City of Foley approved E-J Builders Inc.'s proposal for construction of the Glenlakes Bike Path Phase II on April 21, 2014 in the amount of $127,881.00 per Resolution #14-0144, and,
WHEREAS, E-J Builders Change Order #1 was submitted and approved for and additional $1,672.00 by Resolution #14-0235 for tree removal, and,
WHEREAS, E-J Builders has submitted Change Order #2 for an additive amount of $1,532.40 for additional sod and seeding that were required for the project, and,
WHEREAS, the new cost for E-J Builders to construct the Glenlakes Sidewalk Phase II project is $131,085.40.
NOW THEREFORE BE IT RESOLVED that the City Council of the City of Foley, Alabama, as follows:
SECTION 1: Approves E-J Builders Change Order #2 in the amount of $1,532.40 amending Account No. 12-665-7281, Q64 CONST accordingly.
SECTION 2: This Resolution shall become effective immediately upon its adoption as required by law.