Title
Resolution Approving Capstone's Professional Services Proposal for the Juniper Street Sidewalk Improvements from Azalea Avenue to Hamilton Boulevard
Summary
Description of Topic: (who, what, where, when, why and how much) Capstone submitted a professional services proposal for the pedestrian path project on Juniper Street between Azalea Avenue and Hamilton Boulevard. The project will provide needed sidewalks along Juniper Street to provide additional connectivity in the community. This proposal will allow Capstone to work from beginning of concept to the end of the design of the project.
Budgetary Impact:
Non-Capital Item:
____ Budgeted under account #_______________ (discussion item)
____ Not budgeted, requesting transfer of $__________ from Account #______________ to Account #_____________.**Request to Transfer Departmental Budget Dollars form must be attached**
____ Not budgeted requiring increase to account #___________ in the amount of $____________.**Request to Increase Departmental Budget Dollars form must be attached**
Capital - Departmental **Capital Purchase Worksheet form must be attached**
____ Budgeted under account #______________ for $_________ and described in budget as ________________________. Additional amount needed, if any: Increase in budget of $_________ OR, transfer of $________ from Account #____________ to Account #_____________**Request to Increase OR Request toTransfer Departmental Budget Dollars form must be attached**
____ Not Budgeted - account #____________ requires budget increase of $_____________.**Request to Increase Departmental Budget Dollars form must be attached**
Capital Project - **If requesting to start a project, a Capital Project Worksheet form must be attached**
In current year Capital Projects Plan:
__X___ Yes, described as Ped Paths - Juniper - 98 to Pride planned amount $400,000, requesting $20,000 as total project estimate, including contingencies,...
Click here for full text