Title
West Section Avenue Culvert Repair Bid Award
Summary
DESCRIPTION OF TOPIC: (who, what, when, where, why, and how much)
Recommend awarding the lowest responsible bid submitted by Blade Construction, LLC in the amount of $154,652.95 for the West Section Avenue Culvert Repair project.
SOURCE OF FUNDING:
Please provide the amount requested: $154,652.95
Is this a budgeted item? Yes, but only for $150,000 (resolution 14-0525)
Please provide the budgeted amount: $150,000 Account No. 01-660-8300
If budgeted, is this a capital purchase, capital project, or special fund? _________________________
Was this item included in the Fiscal Year Capital Projects Plan? No
If yes, please provide the amount included in Capital Projects Plan: $___________
Body
WHEREAS, Resolution 14-0525 appropriated $150,000 for the West Section Avenue Culvert Repair Project, and
WHEREAS, the City solicited and publicly opened sealed bids for the project on January 27, 2015 at 2:00 p.m. and the results are as follows:
VENDOR BID AMOUNT
Blade Construction, LLC $154,652.95
Summit Industries, LLC $176,089.65
Ammons & Blackmon, LLC $182,711.25
R&S Paving & Grading, Inc. $206,776.25
Gulf Equipment Corp. $241,217.93
Asphalt Services, Inc. $243,241.25
American Asphalt, Inc. $249,891.00
NOW THEREFORE BE IT RESOLVED that the City Council of the City of Foley, Alabama, as follows:
SECTION 1: Accepts the lowest responsible bid submitted by Blade Construction, LLC in the amount of $154,652.95.
SECTION 2: Appropriates an additional $4,652.95 for the project under Account No. 01-660-8300.
SECTION 3: This Resolution shall become effective immediately upon its adoption as required by law.