Title
Fourth Quarter 2014 Engineering Report
Summary
Engineering Department Project Report
Fourth Quarter 2014
Ashford Park Drainage
- Met with HOAs and property owners
- Surveyed "South" option and evaluated
- Surveying and evaluating alternate "West" route
ATRIP Phase I - Pride Drive
- Awarded to MAC 12/2/14
- Pre-construction conference 1/13/15
ATRIP Phase II - CR 20
- Notice to Proceed 11/20/14
- Work started 1/5/15
ATRIP Phase III - Fern Avenue Extension
- Meeting with ALDOT reps by late January to review desired cross-section
Dog Park
- Parking lot completed
- Separating and bidding remaining work by individual trade
Foley Beach TAP Grant
- Plans under final review week of 1/12/15
- ROW certification Submitted to ALDOT
GCNP Road Extension
- Currently preparing design and cost estimate for Council consideration
Graham Creek Estates Drainage
- Pursuing remaining easements
- Amending engineering scope to add third outfall line
Justice Center Flume
- Notice to Proceed issued 1/7/15
Manning Alleyway Drainage
- Notice to Proceed issued 1/5/15
Pecan Street Mitigation Repair
- Plans under final review week of 1/12/15; preparing to bid
Philomene Holmes Paving
- Baldwin Road Builders have completed this work
Resurfacing Phase V
- MAC started work 1/5/15, plan to finish within the month weather permitting
TIGER Phase I - Shared-Use Paths
- Work started 11/3/14
- Park Avenue substantially complete
- Currently installing sidewalk along W Michigan and piping along W Azalea
TIGER Phase III - Pedestrian Bridge
- Pre-bid conference 1/22/15
- Open bids 2/5/15
UTC Truck Traffic
- Pursuing private agreement to place wayfinding sign along AL 59 north of CR 24
- Requesting directional sign placement from County at BBE/FBE
West Section Drainage Improvements
- Pre-bid 1/22/15
- Open bids 1/27/15