Title
Juniper Street Sidewalk Project
Summary
Description of Topic: (who, what, where, when, why and how much)
Consider appropriating funds, approving bid solicitation, and the construction of a sidewalk along the east side of Juniper Street from CR 20/Miflin Road to Kenny Stabler Avenue.
Budgetary Impact:
Non-Capital Item:
____ Budgeted under account #_______________ (discussion item)
____ Not budgeted, requesting transfer of $__________ from Account #______________ to Account #_____________.
____ Not budgeted requiring increase to account #___________ in the amount of $____________.
Capital - Departmental
____ Budgeted under account #______________ for $___________ and described in budget as __________________________________.
Additional amount needed, if any: Increase in budget of $_____________ OR, transfer of $___________ from Account #____________ to Account #_______________
____ Not Budgeted - account #____________ requires budget increase of $_____________.
Capital Project - **THE PRE-PROJECT CHECKLIST AND BUDGET CHECKLIST MUST BE ATTACHED TO THIS FILE**
In current year Capital Projects Plan:
__x__ Yes, planned amount $60,000________, requesting $60,000______ as total project estimate, including contingencies, under account #12-665-7124 A17 Juniper________
_____ No, requesting $___________ as total project estimate, including contingencies, under account #____________________
Body
WHEREAS, there is a need for a sidewalk along the east side of Juniper Street between CR 20/Miflin Road to Kenny Stabler Avenue, and
WHEREAS, the Engineering Department will be performing the design and will solicit bids for construction.
NOW THEREFORE BE IT RESOLVED that the City Council of the City of Foley, Alabama, as follows:
SECTION 1: Appropriates $60,000.00 for the Juniper Street Sidewalk project, Account No. 12-665-7124 A17 Juniper.
SECTION 2: ...