File #: 24-0274    Version: 1 Name: Resolution Awarding the Bid to Crucible Construction for the New Public Works Complex.
Type: Resolution Status: Adopted
File created: 4/24/2024 In control: City Manager's Office
On agenda: 5/6/2024 Final action: 5/6/2024
Title: A Resolution Approving Bid Award for Foley Public Works Complex- Building Package
Attachments: 1. Foley Public Works Complex - Bid Tabulation Signed, 2. City of Foley Mail - Re_ Foley PWC - Bid Tabulation, 3. Capital Project - PW Building.xlsx - Google Sheets
Title
A Resolution Approving Bid Award for Foley Public Works Complex- Building Package

Summary
Description of Topic: (who, what, where, when, why and how much)
Bids were publicly opened April 11, 2024 with Crucible Construction being the lowest responsible bidder in the amount of $10,624,898.00. EDT-THA recommends awarding the project to Crucible Construction.

Budgetary Impact:
Non-Capital Item:
____ Budgeted under account #_______________ (discussion item)
____ Not budgeted, requesting transfer of $__________ from Account #______________ to Account #_____________.**Request to Transfer Departmental Budget Dollars form must be attached**
____ Not budgeted requiring increase to account #___________ in the amount of $____________.**Request to Increase Departmental Budget Dollars form must be attached**

Capital - Departmental **Capital Purchase Worksheet form must be attached**
____ Budgeted under account #______________ for $_________ and described in budget as ________________________. Additional amount needed, if any: Increase in budget of $_________ OR, transfer of $________ from Account #____________ to Account #_____________**Request to Increase OR Request toTransfer Departmental Budget Dollars form must be attached**
____ Not Budgeted - account #____________ requires budget increase of $_____________.**Request to Increase Departmental Budget Dollars form must be attached**

Capital Project - **If requesting to start a project, a Capital Project Worksheet form must be attached**
In current year Capital Projects Plan:
___X__ Yes, described as _New Public Works Campus__, planned amount $__17,287,742.00___, requesting $_10,800,000.00__ as total project estimate, including contingencies, under account #_400-1060-5100 R66__
_____ No, requesting $___________ as total project estimate, including contingencies, under account #____________________.
__ __ yes, requesting an increase of

Body

...

Click here for full text