File #: 26-0563    Version: 1 Name: A Resolution Amending Resolution No. 26-1261-RES to Rescind the Award to L & K Construction and Award the Highway Safety Improvement Program (HSIP) Project to P. L. Russell Construction, LLC for Pedestrian Improvements Along Highway 98 at Cedar Street, Oa
Type: Resolution Status: Agenda Ready
File created: 10/2/2026 In control: City Council
On agenda: 10/19/2026 Final action:
Title: A Resolution Amending Resolution No. 26-1261-RES to Rescind the Award to L & K Construction and Award the Highway Safety Improvement Program (HSIP) Project to P. L. Russell Construction, LLC for Pedestrian Improvements Along Highway 98 at Cedar Street, Oak Street, Pine Street, Chicago Street, and the Rose Trail Crosswalk
Attachments: 1. 26-1261-RES (3), 2. City of Foley Mail - Follow up about L&K Construction & HSIP project, 3. Joint Termination of Agreement COF and L&K, 4. Bid Proposal Tab - PL Russell LLC, 5. CERTIFIED BID TAB_HSIP-0042(549) - 10-9-2026, 6. Recommendation to Award - PL Russell - HSIP-0042(549) -10-9-2026, 7. Christi-Watkins-Engineering
  • History (0)
  • Text
  • 0 records
Date Ver.Action ByActionResultAction DetailsMeeting DetailsVideo
No records to display.
Title
A Resolution Amending Resolution No. 26-1261-RES to Rescind the Award to L & K Construction and Award the Highway Safety Improvement Program (HSIP) Project to P. L. Russell Construction, LLC for Pedestrian Improvements Along Highway 98 at Cedar Street, Oak Street, Pine Street, Chicago Street, and the Rose Trail Crosswalk

SUMMARY
Amending Resolution No. 26-1261-RES to rescind the award of the Highway Safety Improvement Program (HSIP) project to L & K Construction and award the project to P. L. Russell Construction, LLC, the second-lowest bidder, for $836,557.52. The Alabama Department of Transportation (ALDOT) has confirmed that it will not provide additional funding to cover the $23,758.34 difference between the two bids. Therefore, the City of Foley will be responsible for funding the additional $23,758.34.

Budgetary Impact:
Non-Capital Item:
____ Budgeted under account #_______________ (discussion item)
____ Not budgeted, requesting transfer of $__________ from Account #______________ to Account #_____________.**Request to Transfer Departmental Budget Dollars form must be attached**
____ Not budgeted requiring increase to account #___________ in the amount of $____________.**Request to Increase Departmental Budget Dollars form must be attached**

Capital - Departmental **Capital Purchase Worksheet form must be attached**
____ Budgeted under account #______________ for $_________ and described in budget as ________________________. Additional amount needed, if any: Increase in budget of $_________ OR, transfer of $________ from Account #____________ to Account #_____________**Request to Increase OR Request toTransfer Departmental Budget Dollars form must be attached**
____ Not Budgeted - account #____________ requires budget increase of $_____________.**Request to Increase Departmental Budget Dollars form must be attached**

Capital Project - **If requesting to start a project, a Capital Project Worksheet form mus...

Click here for full text
Legislation Details
Legislation Details (With Text)