Skip to main content
File #: 15-0731    Version: 1 Name: Fairway Drive Entrance Drainage Improvements and Turn Lane
Type: Resolution Status: Adopted
File created: 12/11/2015 In control:
On agenda: 12/21/2015 Final action: 12/21/2015
Title: Fairway Drive Entrance Drainage Improvements and Turn Lane
Attachments: 1. Pre-project Checklist - Fairway Dr. Entrance Drg. Imps. & Turn Ln.

Title

Fairway Drive Entrance Drainage Improvements and Turn Lane

 

Summary

Description of Topic: (who, what, where, when, why and how much)

Consider appropriating funds and approving the solicitation of bids for the construction of the Fairway Drive Entrance Drainage Improvements and Turn Lane project.  This will be an improvement to the Fairway Drive turnout, adding a right turn lane onto Fairway Drive from CR 20.

 

Budgetary Impact:

   Non-Capital Item:

      ____ Budgeted under account #_______________ (discussion item)

      ____ Not budgeted, requesting transfer of $__________ from Account #______________ to Account #_____________.

      ____ Not budgeted requiring increase to account #___________ in the amount of $____________.

 

   Capital - Departmental

      ____ Budgeted under account #______________ for $___________ and described in budget as __________________________________.

                    Additional amount needed, if any: Increase in budget of  $_____________ OR, transfer of $___________ from Account #____________ to Account #_______________

      ____ Not Budgeted - account #____________ requires budget increase of $_____________.

 

   Capital Project - **THE PRE-PROJECT CHECKLIST AND BUDGET CHECKLIST MUST BE ATTACHED TO THIS FILE**

      In current year Capital Projects Plan: 

        ___X_ Yes, planned amount $105,750_____, requesting $105,750_____ as total project estimate, including contingencies, under account #12-665-7367____________

        _____ No, requesting $___________ as total project estimate, including contingencies, under account #____________________

 

Body

 

    WHEREAS, the existing Fairway Drive turnout has reached the end of its service life, and

 

    WHEREAS, drainage improvements are needed as well as adding a right turn lane onto Fairway Drive from County Road 20, and

 

    WHEREAS, $36,825 was added to the FY16 planning document for the Fairway Drive Entrance Drainage Improvements under account 12-665-7128, and

 

    WHEREAS, $68,925  was added to the FY16 planning document for the Fairway Drive Turn Lane project under account pending, and

 

    WHEREAS, the project will be completed under one bid and one contractor, the amounts are being combined into one account, 12-665-7367.

 

    NOW THEREFORE BE IT RESOLVED that the City Council of the City of Foley, Alabama, as follows:

 

    SECTION 1:     Appropriates funds in the amount of $105,750.00 and approves the solicitation of bids for the referenced project for Account No. 12-665-7367.

 

    SECTION 2:     This Resolution shall become effective immediately upon its adoption as required by law.