File #: 23-0060    Version: 1 Name: A Resolution to Approve the Road Building Project on South Pecan Street and Permission to go to Bid.
Type: Resolution Status: Removed
File created: 1/27/2023 In control: City Manager's Office
On agenda: 2/20/2023 Final action: 2/20/2023
Title: A Resolution to Approve the Road Building Project on South Pecan Street and Permission to go to Bid.
Attachments: 1. Capital Purchase - Capital Project Worksheet Shop truck.xlsx - Capital Project

Title

A Resolution to Approve the Road Building Project on South Pecan Street and Permission to go to Bid.

 

Summary

The extension of South Pecan Street from Lay Lane southward to the north round-a-bout on Pride Drive is estimated to cost $763,000. This is a planned City constructed road for FY23, budgeted for the amount of $405,000. The Street Department is requesting to increase the funds by $358,000, under Account #400-3010-5100 CR-1, totaling in the amount of $763,000. Out of the road building components, Street Department plans to go to bid for the asphalt surfacing and masonry work. Street Department expects six to nine months for the road to be completed.

 

 Budgetary Impact:

   Non-Capital Item:

      ____ Budgeted under account #_______________ (discussion item)

      ____ Not budgeted, requesting transfer of $__________ from Account #______________ to Account #_____________.**Request to Transfer Departmental Budget Dollars form must be attached**

      ____ Not budgeted requiring increase to account #___________ in the amount of $____________.**Request to Increase Departmental Budget Dollars form must be attached**

 

   Capital - Departmental **Capital Purchase Worksheet form must be attached**

      ____ Budgeted under account #______________ for $_________ and described in budget as ________________________. Additional amount needed, if any: Increase in budget of  $_________ OR, transfer of $________ from Account #____________ to Account #_____________**Request to Increase OR Request toTransfer Departmental Budget Dollars form must be attached**

      ____ Not Budgeted - account #____________ requires budget increase of $_____________.**Request to Increase Departmental Budget Dollars form must be attached**

 

   Capital Project - **If requesting to start a project, a Capital Project Worksheet form must be attached**

      In current year Capital Projects Plan: 

        ___X__ Yes, described as _South Pecan (Lay to Pride) (CR-1)__, planned amount $_405,000  , requesting $763,000__as total project estimate, including contingencies, under account #_400-3010-5100 CR-1_

        _____ No, requesting $___________ as total project estimate, including contingencies, under account #____________________.

        _____ No, requesting an increase of $___________ to an already approved project titled ________________________ that is being tracked under Account No. ___________________.

 

Body

 

     WHEREAS, the extension of South Pecan Street from Lay Lane southward to the north round-a-bout on Pride Drive is estimated to cost $763,000, AND 

     WHEREAS, this is a planned City constructed road project for FY23, budgeted for the amount of $405,000, AND

     WHEREAS, the Street Department is requesting to increase this project by $358,000, for a total of $763,000 under Account #400-3010-5100 CR-1, AND

     WHEREAS, out of the road building components, the Street Department plans to go to bid for the asphalt surfacing and masonry work, AND

     WHEREAS, the Street Department expects six to nine months for the road to be completed.

 

     NOW THEREFORE BE IT RESOLVED that the City Council of the City of Foley, Alabama, as follows:

 

     SECTION 1:     Approves the extension of South Pecan Street from Lay Lane southward to the north round-a-bout on Pride Drive.

     SECTION 2:     Approves increasing the planned project by $358,000, for a total of $763,000 and amends account #400-3010-5100 CR-1 accordingly.

     SECTION 3:     Approves permission for Street Department to go to bid for the asphalt paving component and masonry work of the road building project.

     SECTION 4:     Acknowledges that the Street Department is estimating six to nine months for the South Pecan extension to be completed.

     SECTION 5:     This Resolution shall become effective immediately upon its adoption as required by law.