Skip to main content
File #: 23-0091    Version: 1 Name: A Resolution Approving the Application to the FY23 Rebuilding American Infrastructure with Sustainability and Equity (RAISE) Grant Program
Type: Resolution Status: Adopted
File created: 2/10/2023 In control: City Council
On agenda: 2/20/2023 Final action: 2/20/2023
Title: A Resolution Approving the Application to the FY23 Rebuilding American Infrastructure with Sustainability and Equity (RAISE) Grant Program
Attachments: 1. FY 2023 RAISE NOFO 12.14.2022

Title

A Resolution Approving the Application to the FY23 Rebuilding American Infrastructure with Sustainability and Equity (RAISE) Grant Program

 

Summary

The Engineering Department requests permission to apply for the FY23 Rebuilding American Infrastructure with Sustainability and Equity (RAISE) Grant Program. The applications are due February 28, 2023. The minimum grant award for a rural community is $1,000,000 with 20% matching funds required. The Capstone Engineering Group is working on this grant application to be submitted by the City of Foley. The intended project would create access and lighting improvements along Hwy 59 and Hwy 98.

 

                     

Budgetary Impact:

   Non-Capital Item:

      ____ Budgeted under account #_______________ (discussion item)

      ____ Not budgeted, requesting transfer of $__________ from Account #______________ to Account #_____________.

      ____ Not budgeted requiring increase to account #___________ in the amount of $____________.

 

   Capital - Departmental

____ Budgeted under account #______________ for $___________ and described in budget as __________________________________.

____Additional amount needed, if any: Increase in budget of $_____________ OR, transfer of $___________ from Account #____________ to Account #_______________    

___ Not Budgeted - account # __________________________ requires budget increase of ____________.

 

   Capital Project - **THE PRE-PROJECT CHECKLIST AND BUDGET CHECKLIST MUST BE ATTACHED TO THIS FILE**

      In current year Capital Projects Plan: 

        _____ Yes, planned amount $___________, requesting $_________ as total project estimate, including contingencies, under account #_________________

        _____ No, requesting $___________ as total project estimate, including contingencies, under account #____________________

 

Body

 

     WHEREAS, the Engineering Department requests permission to apply for the FY23 Rebuilding American Infrastructure with Sustainability and Equity (RAISE) Grant Program, and

 

     WHEREAS, the minimum grant award is $1,000,000 with 20% matching funds required with applications due February 28, 2023, and

 

     WHEREAS, the Capstone Engineering Group is working on this grant application to be submitted by the City of Foley, and

 

     WHEREAS, the intended project would create access and lighting improvements along Hwy 59 and Hwy 98.

 

     NOW THEREFORE BE IT RESOLVED that the City Council of the City of Foley, Alabama, as follows:

 

     SECTION 1: Approves the Engineering Department’s request to submit an application to the FY23 Rebuilding American Infrastructure with Sustainability and Equity (RAISE) Grant Program and authorizes matching funds if awarded.

 

     SECTION 2: Council authorizes Mayor and other City officials to sign the application and other documents required to proceed grant request.

 

     SECTION 3: This Resolution shall become effective immediately upon its adoption as required by law.