File #: 14-0413    Version: 1 Name: Change Order No. 1 for Glenlakes Bike Path Ph. II
Type: Resolution Status: Adopted
File created: 6/6/2014 In control:
On agenda: 6/16/2014 Final action: 6/16/2014
Title: Change Order No. 1 for Glenlakes Bike Path Ph. II
Attachments: 1. E-J Builders Change Order
Related files: 14-0672, 14-0704
Title
Change Order No. 1 for Glenlakes Bike Path Ph. II
 
Summary
DESCRIPTION OF TOPIC: (who, what, when, where, why, and how much)
Approve Change Order No. 1 from E-J Builders, Inc. for work caused by change in conditions of project area.
 
 
SOURCE OF FUNDING:
Please provide the amount requested: $19,764.00
Is this a budgeted item? No      
Please provide the budgeted amount: $127,811.00   Account No. 12-665-7281 Q64 CONST
If budgeted, is this a capital purchase, capital project, or special fund?      _________________________  
Was this item included in the Fiscal Year Capital Projects Plan?   Yes/No
If yes, please provide the amount included in Capital Projects Plan: $___________
 
 
Body
 
WHEREAS, E-J Builders, Inc. was awarded the construction contract for the Glenlakes Bike Path Ph. II per Resolution No. 14-0144 on April 21, 2014, and
WHEREAS, due to the record rain event of April 29, 2014, FEMA Event #4176-DR-AL, changes in conditions within the project location caused the Contractor to restore the project area to pre-storm conditions and removal of one tree not related to the record rain event, and
WHEREAS, a property owner in the project area wishes to add an additional pipe to a driveway to mediate further problems and it is City practice to install pipe in the right-of-ways and bill property owners for the cost, and
WHEREAS, Change Order No. 1 was submitted by the Contractor to the Engineering Department as follows:
      Pre-storm restoration:  $15,240.16
      Tree removal (unrelated to rain event):  $1,672.00
      Pipe to be reimbursed by Owner:  $2,851.84
NOW THEREFORE BE IT RESOLVED that the City Council of the City of Foley, Alabama, as follows:
SECTION 1:       Approves E-J Builders, Inc.'s Change Order No. 1 in the total amount of $19,764.00 for work related to the Glenlakes Bike Path Ph. II project area,
SECTION 2:    Appropriates $15,240.16 for work related to restoring the area to pre-storm conditions to Account No. 01-660-8300
SECTION 3:    Appropriates $1,672.00 for tree removal to Account No. 12-665-7281 Q64 CONST accordingly.
SECTION 4:    Account 01-624-8010 will be used to record the $2,851.84 cost and reimbursement by the property owner.
SECTION 5:      This Resolution shall become effective immediately upon its adoption as required by law.