File #: 19-0203    Version: 1 Name: A RESOLUTION APPROVING CHESTNUT STREET PIPE IMPROVEMENTS PROJECT
Type: Resolution Status: Adopted
File created: 4/3/2019 In control:
On agenda: 4/15/2019 Final action: 4/15/2019
Title: A RESOLUTION APPROVING CHESTNUT STREET PIPE IMPROVEMENTS PROJECT
Attachments: 1. Capital Project Worksheet

Title

A RESOLUTION APPROVING CHESTNUT STREET PIPE IMPROVEMENTS PROJECT

 

Summary

Description of Topic: (who, what, where, when, why and how much)

The existing pipe geometry beneath Azalea and the lack of a pipe beneath Chestnut causes standing water for days which is a street maintenance issue and also a public nuisance with mosquitoes. We plan on adding a secondary storm drainage pipe, 22"x14", beneath Azalea Avenue at Chestnut Street intersection, and aslo add an 18"x11" pipe beneath Chestnut to alleviate the standing water and poor drainage issue on the south side of Azalea. The project is expected to be completed by Public Works Department and is expected to be completed at budget of $12,500.00.

 

Budgetary Impact:

   Non-Capital Item:

      ____ Budgeted under account #_______________ (discussion item)

      ____ Not budgeted, requesting transfer of $__________ from Account #______________ to Account #_____________.**Request to Transfer Departmental Budget Dollars form must be attached**

      ____ Not budgeted requiring increase to account #___________ in the amount of $____________.**Request to Increase Departmental Budget Dollars form must be attached**

 

   Capital - Departmental **Capital Purchase Worksheet form must be attached**

      ____ Budgeted under account #______________ for $_________ and described in budget as ________________________. Additional amount needed, if any: Increase in budget of  $_________ OR, transfer of $________ from Account #____________ to Account #_____________**Request to Increase OR Request toTransfer Departmental Budget Dollars form must be attached**

      ____ Not Budgeted - account #____________ requires budget increase of $_____________.**Request to Increase Departmental Budget Dollars form must be attached**

 

   Capital Project - **If requesting to start a project, a Capital Project Worksheet form must be attached**

      In current year Capital Projects Plan: 

        __X__ Yes, described as Chestnut Street Pipe Improvement, planned amount $12,500, requesting $12,500.00 as total project estimate, including contingencies, under account # 400-3020-5102 A19-Chestnut - Drainage Improvement

        _____ No, requesting $___________ as total project estimate, including contingencies, under account #____________________.

        _____ No, requesting an increase of $___________ to an already approved project titled ________________________ that is being tracked under Account No. ___________________.

 

Body

 

                     WHEREAS,                     The existing pipe geometry beneath Azalea and the lack of a pipe beneath Chestnut causes standing water for days which is a street maintenance issue and also a public nuisance with mosquitoes, and

 

                     WHEREAS,                     We plan on adding a secondary storm drainage pipe, 22"x14", beneath Azalea Avenue at Chestnut Street intersection, and will also add an 18"x11" pipe beneath Chestnut to alleviate the standing water and poor drainage issue on the south side of Azalea, and

 

                     WHEREAS,                     Public Works Department will complete the project.

                       

                     NOW THEREFORE BE IT RESOLVED that the City Council of the City of Foley, Alabama, as follows:

 

                          SECTION 1:                     Approves the Chestnut Street Pipe Improvement Project and appropriates funds in the amount of up to $12,500.00 under Account No. 400-3020-5102 A19-Chestnut - Drainage Improvement.

                         

                          SECTION 2:                     This Resolution shall become effective immediately upon its adoption as required by law.