File #: 24-0002    Version: 1 Name: a Resolution Approving an Increase in Funds for South Pecan Street Extension.
Type: Resolution Status: Adopted
File created: 12/19/2023 In control: City Manager's Office
On agenda: 1/2/2024 Final action: 1/2/2024
Title: A Resolution Approving an Increase in Funds for South Pecan Street Extension.
Attachments: 1. 21-1271 RES S Pecan Funding, 2. Budget Increase -S Pecan St

Title

A Resolution Approving an Increase in Funds for South Pecan Street Extension.

 

Summary

On August 2, 2021, Resolution 21-1271 appropriated $405,000.00 to account 400-3010-5100 CR-1 for the South Pecan Street Extension. To complete the project additional sidewalks, guard rails, crosswalks, armoring and landscaping is needed, estimating close to $382,000. The Street Departments requests an additional $400,000.00 to account # 400-3010-5100 CR-1 to cover any unidentified occurrences.

 

Budgetary Impact:

   Non-Capital Item:

      ____ Budgeted under account #_______________ (discussion item)

      ____ Not budgeted, requesting transfer of $__________ from Account #______________ to Account #_____________.

      ____ Not budgeted requiring increase to account # _____________in the amount of $_______ (expense budgeted, need to budget revenue only)

 

   Capital - Departmental

      ____ Budgeted under account #______________ for $___________ and described in budget as __________________________________.

                    Additional amount needed, if any: Increase in budget of  $_____________ OR, transfer of $___________ from Account #____________ to Account #_______________

      ____ Not Budgeted - account #____________ requires budget increase of $_____________.

 

   Capital Project - **THE PRE-PROJECT CHECKLIST AND BUDGET CHECKLIST MUST BE ATTACHED TO THIS FILE**

      In current year Capital Projects Plan: 

        ___X__ Yes, planned amount $405,000.00 budgeted under account #400-5010-5100 and described in budget as South Pecan (lay to Pride) (CR-1), but requiring increase of $400,000.00 to the GL account to proceed.

        _____ No, requesting $___________ as total project estimate, including contingencies, under account #____________________

 

Body

     WHEREAS, Resolution 21-1271 appropriated $405,000.00 to account # 400-3010-5100 CR-1 for the South Pecan St Extension, and

 

     WHEREAS, additional sidewalks, guard rails, crosswalks, armoring and landscaping is needed, and

 

     WHEREAS, the Street Department is requesting an additional $400,000.00 under account #400-3010-5100 CR-1 to complete the project.

 

     NOW THEREFORE BE IT RESOLVED that the City Council of the City of Foley, Alabama, as follows:

 

     SECTION 1: Approves the increase in budget and appropriates $400,000.00 under account #400-3010-5100 CR-1.