File #: 24-0728    Version: 1 Name: Recommend Appropriating Additional Funds for Phase Two of the Heritage Park Electrical Upgrades and Park Improvements
Type: Resolution Status: Adopted
File created: 11/25/2024 In control:
On agenda: 12/2/2024 Final action: 12/2/2024
Title: A Resolution Appropriating Additional Funds for Phase Two of the Heritage Park Electrical Upgrades and Park Improvements
Attachments: 1. Daisha-Barnes-Engineering (10), 2. Foley Heritage Park Proposed Lighting Option B2

Title

A Resolution Appropriating Additional Funds for Phase Two of the Heritage Park Electrical Upgrades and Park Improvements

 

Summary

Description of Topic: (who, what, where, when, why and how much) We received a bid of $350,000.00 for our ongoing Heritage Park Improvements project and are requesting an additional $183,000.00 to complete Phase Two the project and install lighting upgrades through Riviera and in-ground vaults with removable pedestals on the east side of the park.

 

Budgetary Impact:

   Non-Capital Item:

      ____ Budgeted under account #_______________ (discussion item)

      ____ Not budgeted, requesting transfer of $__________ from Account #______________ to Account #_____________.**Request to Transfer Departmental Budget Dollars form must be attached**

      ____ Not budgeted requiring increase to account #___________ in the amount of $____________.**Request to Increase Departmental Budget Dollars form must be attached**

 

   Capital - Departmental **Capital Purchase Worksheet form must be attached**

      ____ Budgeted under account #______________ for $_________ and described in budget as ________________________. Additional amount needed, if any: Increase in budget of  $_________ OR, transfer of $________ from Account #____________ to Account #_____________**Request to Increase OR Request toTransfer Departmental Budget Dollars form must be attached**

      ____ Not Budgeted - account #____________ requires budget increase of $_____________.**Request to Increase Departmental Budget Dollars form must be attached**

 

   Capital Project - **If requesting to start a project, a Capital Project Worksheet form must be attached**

      In current year Capital Projects Plan: 

        __X___ Yes, described as Heritage Park Improvements, planned amount $183,000.00, requesting $183,000.00 as total project estimate, including contingencies, under account #400-5010-5101

        _____ No, requesting $___________ as total project estimate, including contingencies, under account #____________________.

        _____ Yes, requesting an increase of $___________ to an already approved project titled ________________________ that is being tracked under Account No. ___________________.

        _____ No, requesting an increase of $__________ to an already approved project titled _______________________ that is being tracked under Account No. _________________.

 

Body

 

     WHEREAS,  We received a bid of $350,000.00 for our Heritage Park Improvements project, and

 

     WHEREAS,  we are negotiating the price with the contractor and have reached out for additional quotes, and

 

     WHEREAS,  we request to appropriate $183,000.00 to complete the project and installing lighting upgrades through Riviera and in-ground vaults with removable pedestals on the east side of the park.

 

     NOW THEREFORE BE IT RESOLVED that the City Council of the City of Foley, Alabama, as follows:

 

     SECTION 1:     Approve and appropriate $183,000.00 to complete the Heritage Park Electrical Upgrades and Park Improvements project to include installing lighting upgrades through Riviera and in-ground vaults with removable pedestals on the east side of the park under Account No. #400-5010-5101

 

     SECTION 2:     This Resolution shall become effective immediately upon its adoption as required by law.