File #: 23-0701    Version: 1 Name: A Resolution to Approve and Beulah Heights Stormwater Management Plan
Type: Resolution Status: Adopted
File created: 12/11/2023 In control: Community Development Deptartment
On agenda: 12/18/2023 Final action: 12/18/2023
Title: A Resolution Approving the Beulah Heights Stormwater Management Plan
Attachments: 1. Beulah Heights SMP_Final
Related files: 23-0083

Title

A Resolution Approving the Beulah Heights Stormwater Management Plan

 

Summary

The Environmental Department request the approval and support of the Beulah Heights Stormwater Management Plan which was developed by Thompson Engineering through the Alabama Coastal Area Management Plan Grant by the AL Department of Conservation and Natural Resources. Support is being requested to implement the priority stormwater management measures identified in the plan as well as establish the septic system rehabilitation and sewer connection program. No funding is requested at this time as we plan to seek grants to fund the priority measures. We are also seeking donations to fund the pathogen reduction through the septic/sewer program.

 

Budgetary Impact: NA

   Non-Capital Item:

      ____ Budgeted under account #_______________ (discussion item)

      ____ Not budgeted, requesting transfer of $__________ from Account #______________ to Account #_____________.**Request to Transfer Departmental Budget Dollars form must be attached**

      ____ Not budgeted requiring increase to account #___________ in the amount of $____________.**Request to Increase Departmental Budget Dollars form must be attached**

 

   Capital - Departmental **Capital Purchase Worksheet form must be attached**

      ____ Budgeted under account #______________ for $_________ and described in budget as ________________________. Additional amount needed, if any: Increase in budget of  $_________ OR, transfer of $________ from Account #____________ to Account #_____________**Request to Increase OR Request toTransfer Departmental Budget Dollars form must be attached**

      ____ Not Budgeted - account #____________ requires budget increase of $_____________.**Request to Increase Departmental Budget Dollars form must be attached**

 

   Capital Project - **If requesting to start a project, a Capital Project Worksheet form must be attached**

      In current year Capital Projects Plan: 

        _____ Yes, described as __________________________, planned amount $___________, requesting $_________ as total project estimate, including contingencies, under account #_________________

        _____ No, requesting $___________ as total project estimate, including contingencies, under account #____________________.

        _____ Yes, requesting an increase of $___________ to an already approved project titled ________________________ that is being tracked under Account No. ___________________.

        _____ No, requesting an increase of $__________ to an already approved project titled _______________________ that is being tracked under Account No. _________________.

 

Body

 

     WHEREAS, the City of Foley received the Alabama Coastal Area Management Plan Grant from the AL Department of Conservation and Natural Resources in 2023 for the development of the Beulah Heights Stormwater Management Plan to provide a roadmap addressing stormwater flooding and non point source pollutants in the Beulah Heights Community, and

     WHEREAS, the plan was completed in September 2023 with prioritization of stormwater management measures and establishment of a septic system rehabilitation and sewer connection program, and

     WHEREAS, the Environmental Department is requesting approval and support for implementing the Beulah Heights Stormwater Management Plan.

     NOW THEREFORE BE IT RESOLVED that the City Council of the City of Foley, Alabama, as follows:

     SECTION 1:     Approves the support of the Beulah Heights Stormwater Management Plan with implementation of the priority stormwater management measures and establishment of a septic system rehabilitation and sewer connection program.

     SECTION 2:     This Resolution shall become effective immediately upon its adoption as required by law.