File #: 17-0078    Version: 1 Name: TIGER Phase 3 Change Order #3
Type: Resolution Status: Adopted
File created: 1/30/2017 In control:
On agenda: 2/6/2017 Final action: 2/6/2017
Title: TIGER Phase 3 Change Order #3
Attachments: 1. Change Order #3

Title

TIGER Phase 3 Change Order #3

 

Summary

Description of Topic: (who, what, where, when, why and how much)

Approve Morette Company, Inc.'s Change Order #3 and grant additional contract days.

 

Budgetary Impact:

   Non-Capital Item:

      ____ Budgeted under account #_______________ (discussion item)

      ____ Not budgeted, requesting transfer of $__________ from Account #______________ to Account #_____________.

      ____ Not budgeted requiring increase to account #___________ in the amount of $____________.

 

   Capital - Departmental

      ____ Budgeted under account #______________ for $___________ and described in budget as __________________________________.

                    Additional amount needed, if any: Increase in budget of  $_____________ OR, transfer of $___________ from Account #____________ to Account #_______________

      ____ Not Budgeted - account #____________ requires budget increase of $_____________.

 

   Capital Project - **THE PRE-PROJECT CHECKLIST AND BUDGET CHECKLIST MUST BE ATTACHED TO THIS FILE**

      In current year Capital Projects Plan: 

        __x___ Yes, planned amount $_no additional funds_______, requesting $_________ as total project estimate, including contingencies, under account #31-665-7300________

        _____ No, requesting $___________ as total project estimate, including contingencies, under account #____________________

Body

 

     WHEREAS, the TIGER Phase 3 project is substantially complete and the overall TIGER Grant is nearing final closeout, and

     WHEREAS, the Engineering Department is recommending the approval of Change Order #3 to adjust all quantities and account for engineering and architectural changes made during construction.

 

     NOW THEREFORE BE IT RESOLVED that the City Council of the City of Foley, Alabama, as follows:

 

     SECTION 1:     Approves Change Order #3 in favor of Morette Company, Inc. in the amount of $43,349.52 and grants fifteen (15) additional contract days for Account No. 31-665-7300 no additional funds are needed.

     SECTION 2:     This Resolution shall become effective immediately upon its adoption as required by law.