Title
City of Foley Fiber System Expansion for the Foley Sports Tourism Complex
Summary
The City is currently paying for a Southern Light internet circuit at the Event Center to support our City staff and operations during events. We wish to connect, via fiber optic cable, the Championship Field, Maintenance Shed, and FIeld House to further support the operations of the Sports Tourism Department and provide them greater flexibility and capability in meeting the needs of the event stakeholders.
Budgetary Impact:
Non-Capital Item:
____ Budgeted under account #_______________ (discussion item)
____ Not budgeted, requesting transfer of $__________ from Account #______________ to Account #_____________.
____ Not budgeted requiring increase to account #___________ in the amount of $____________.
Capital - Departmental
____ Budgeted under account #______________ for $___________ and described in budget as __________________________________.
Additional amount needed, if any: Increase in budget of $_____________ OR, transfer of $___________ from Account #____________ to Account #_______________
____ Not Budgeted - account #____________ requires budget increase of $_____________.
Capital Project - **THE PRE-PROJECT CHECKLIST AND BUDGET CHECKLIST MUST BE ATTACHED TO THIS FILE**
In current year Capital Projects Plan:
___X__ Yes, planned amount $_15,500_, requesting $__14,547.70_ as total project estimate, including contingencies, under account #_12-665-7129 A21 S-TOUR___
_____ No, requesting $___________ as total project estimate, including contingencies, under account #____________________
Body
WHEREAS, the Sports Tourism Department needs reliable, wired, city-connected internet service at all of the buildings of the Foley Sports Tourism Complex,
WHEREAS, this project is in the FY 18 Capital Projects Planning Document.
NOW THEREFORE BE IT RESOLVED that the City Council of the City of Foley, Alabama, as follows:
SECTION 1: Appropriates $14,547.70 for the Fiber System Expansion at the Foley Sports Tourism Complex, Account No. 12-665-7129 A21 S-TOUR.
SECTION 2: Approves the expenditure for fiber system construction and installation of network equipment to establish connectivity at the buildings.
SECTION 3: This Resolution shall become effective immediately upon its adoption as required by law.