Skip to main content
File #: 17-0667    Version: 1 Name: 9th Avenue Extension Project
Type: Resolution Status: Adopted
File created: 11/13/2017 In control:
On agenda: 11/20/2017 Final action: 11/20/2017
Title: 9th Avenue Extension Project
Attachments: 1. BCBE Letter, 2. HMR Contract, 3. Pre-Project Checklist

Title

9th Avenue Extension Project

 

Summary

Description of Topic: (who, what, where, when, why and how much)

Consider appropriating funds and approving Hutchinson, Moore & Rauch, LLC's contract for the design and bidding of the 9th Avenue Extension project.

 

Budgetary Impact:

   Non-Capital Item:

      ____ Budgeted under account #_______________ (discussion item)

      ____ Not budgeted, requesting transfer of $__________ from Account #______________ to Account #_____________.

      ____ Not budgeted requiring increase to account #___________ in the amount of $____________.

 

   Capital - Departmental

      ____ Budgeted under account #______________ for $___________ and described in budget as __________________________________.

                    Additional amount needed, if any: Increase in budget of  $_____________ OR, transfer of $___________ from Account #____________ to Account #_______________

      ____ Not Budgeted - account #____________ requires budget increase of $_____________.

 

   Capital Project - **THE PRE-PROJECT CHECKLIST AND BUDGET CHECKLIST MUST BE ATTACHED TO THIS FILE**

      In current year Capital Projects Plan: 

        __x__ Yes, planned amount $812,500_______, requesting $812,500______ as total project estimate, including contingencies, under account #12-665-7386 R33 PROF/CONST_

        _____ No, requesting $___________ as total project estimate, including contingencies, under account #____________________

 

Body

 

     WHEREAS, there is a need to extend 9th Avenue from Cedar Street to Hickory Street, and

    

     WHEREAS, a proposal has been solicited from Hutchinson, Moore & Rauch, LLC for the roadway design and bid process, and

 

     WHEREAS, the 9th Avenue Extension project is in the FY18 Capital Projects Planning Document.

    

     NOW THEREFORE BE IT RESOLVED that the City Council of the City of Foley, Alabama, as follows:

    

     SECTION 1:     Appropriates $812,500.00 for the 9th Avenue Extension project for Account No. 12-665-7386 R33 PROF/CONST.

 

     SECTION 2:     Approves Hutchinson, Moore & Rauch, LLC's contract for design and bidding in the amount of $71,900.00 for Account No. 12-665-7386 R33 PROF/CONST.

    

     SECTION 3:     This Resolution shall become effective immediately upon its adoption as required by law.