File #: 23-0326    Version: 1 Name: Resolution Approving the Pride Blvd Sidewalk Project.Sidewalk Project.
Type: Resolution Status: Adopted
File created: 5/31/2023 In control: City Manager's Office
On agenda: 8/7/2023 Final action: 8/7/2023
Title: Resolution Approving the Pride Blvd Sidewalk Project.
Attachments: 1. James Bros Quote, 2. Capital Project Pride

Title

Resolution Approving the Pride Blvd Sidewalk Project.

 

Summary

In the capital projects for FY23 budget, $100,000 was planned under Account # 400-3010-5101 for Sidewalk Improvements - Throughout the City. The Street Department is asking for $147,200.00 in funds under Account # 400-3010-5101 for Sidewalk Improvements - Throughout the City for the Pride Blvd Sidewalk Project.

 

Budgetary Impact:

   Non-Capital Item:

      ____ Budgeted under account #_______________ (discussion item)

      ____ Not budgeted, requesting transfer of $__________ from Account #______________ to Account #_____________.**Request to Transfer Departmental Budget Dollars form must be attached**

      ____ Not budgeted requiring increase to account #___________ in the amount of $____________.**Request to Increase Departmental Budget Dollars form must be attached**

 

   Capital - Departmental **Capital Purchase Worksheet form must be attached**

      ____ Budgeted under account #_________ for $________requesting an additional __________and described in budget as ____________.

Additional amount needed, if any: Increase in budget of  $___________OR, transfer of $________ from Account #____________ to Account #_____________**Request to Increase OR Request toTransfer Departmental Budget Dollars form must be attached**

      ____ Not Budgeted - account #_ ________ requires budget increase of $__________.**Request to Increase Departmental Budget Dollars form must be attached**

 

   Capital Project - **If requesting to start a project, a Capital Project Worksheet form must be attached**

      In current year Capital Projects Plan: 

        __X__ Yes, described as _Sidewalk Improvements - Throughout the City_, planned amount $_100,000.00_, requesting $__ 147,200.00_ as total project estimate, including contingencies, under account #_400-3010-5101 A23 Pride

        __ __ No, requesting $_                         __ as total project estimate, including contingencies, under account #_                     __.

        _____ No, requesting an increase of $___________ to an already approved project titled ________________________ that is being tracked under Account No. ___________________.

 

 

 

Body

     WHEREAS, in the capital projects for FY23 budget, $100,000 was approved under Account # 400-3010-5101 for Sidewalk Improvements - Throughout the City, and

     WHEREAS, the proposed sidewalk project is estimated at $147,200.00, and

     WHEREAS, the Street Department is asking for approval of the sidewalk project as listed below.

    

     NOW THEREFORE BE IT RESOLVED that the City Council of the City of Foley, Alabama, as follows:

     SECTION 1:     Approves the new sidewalk and appropriates $147,200.00 to Sidewalk Construction account # 400-3010-5101 A23 Pride for the Pride Blvd Sidewalk Project.  

     SECTION 2:     This Resolution shall become effective immediately upon its adoption.