Title
A Resolution Approving Volkert, Inc Contract for Environmental Assessment for New Library Building
Summary
Under Resolution 23-1091, the Council approved the acceptance of the $2 million in HUD Community Project Funding for the new library construction. HUD requires as part of this agreement that an environmental assessment be completed on the site prior to construction. As the City is unable to conduct these assessments on our own, we have obtained a proposal from Volkert, Inc as they have direct experience with HUD funded projects. We request to accept the proposal submitted by Volkert Inc in the amount of $102,654.51 and amend the budget accordingly. If we do not move forward with this environmental assessment, they we will not be eligible for the $2m in HUD project funding.
Budgetary Impact:
Non-Capital Item:
____ Budgeted under account #_______________ (discussion item)
____ Not budgeted, requesting transfer of $__________ from Account #______________ to Account #_____________.**Request to Transfer Departmental Budget Dollars form must be attached**
____ Not budgeted requiring increase to account #___________ in the amount of $____________.**Request to Increase Departmental Budget Dollars form must be attached**
Capital - Departmental **Capital Purchase Worksheet form must be attached**
____ Budgeted under account #______________ for $_________ and described in budget as ________________________. Additional amount needed, if any: Increase in budget of $_________ OR, transfer of $________ from Account #____________ to Account #_____________**Request to Increase OR Request toTransfer Departmental Budget Dollars form must be attached**
____ Not Budgeted - account #____________ requires budget increase of $_____________.**Request to Increase Departmental Budget Dollars form must be attached**
Capital Project - **If requesting to start a project, a Capital Project Worksheet form must be attached**
In current year Capital Projects Plan:
__X__ Yes, described as New Library Building, planned amount $1,320,451.73, requesting increase of $102,654.51 as total project estimate, including contingencies, under account #400-5020-5101
_____ No, requesting $_____________ as total project estimate, including contingencies, under account #___________________.
_____ No, requesting an increase of $___________ to an already approved project titled ________________________ that is being tracked under Account No. ___________________.
Body
WHEREAS, Under Resolution 23-1091, the Council approved the acceptance of the $2 million in HUD Community Project Funding for the new library construction, and
WHEREAS, HUD requires as part of this agreement that an environmental assessment be completed on the site prior to construction, and
WHEREAS, as the City is unable to conduct these assessments on our own, we have obtained a proposal from Volkert, Inc as they have direct experience with HUD funded projects, and
WHEREAS, we request to accept the proposal submitted by Volkert, Inc in the amount of $102,654.51 and amend the budget accordingly.
NOW THEREFORE BE IT RESOLVED that the City Council of the City of Foley, Alabama, as follows:
SECTION 1: Accepts the proposal for Professional Services from Volkert, Inc for an Environmental Assessment of the property where the new library will be constructed, and
SECTION 2: Appropriates funds in the amount of $102,654.51 under Account No. 400-5020-5101.
SECTION 3: Authorizes the Mayor or other City officials to execute the Volkert, Inc agreement.