File #: 17-0324    Version: 1 Name: Foley Beach Express ​Guardrail Relocation​ Safety Project
Type: Resolution Status: Adopted
File created: 6/6/2017 In control:
On agenda: 7/5/2017 Final action: 7/5/2017
Title: Foley Beach Express ?Guardrail Relocation? Safety Project
Attachments: 1. C&H Const. Proposal for Guardrail, 2. FBE Guardrail Layout, 3. Pre-project Checklist for FBE Guardrail

Title

Foley Beach Express ​Guardrail Relocation​ Safety Project

 

Summary

Description of Topic: (who, what, where, when, why and how much)

Consider appropriating funds for the safety project involving the relocation of the existing guardrail along the Foley Beach Express between CR 20/Miflin Road and CR 12.

 

Budgetary Impact:

   Non-Capital Item:

      ____ Budgeted under account #_______________ (discussion item)

      ____ Not budgeted, requesting transfer of $__________ from Account #______________ to Account #_____________.

      ____ Not budgeted requiring increase to account #___________ in the amount of $____________.

 

   Capital - Departmental

      ____ Budgeted under account #______________ for $___________ and described in budget as __________________________________.

                    Additional amount needed, if any: Increase in budget of  $_____________ OR, transfer of $___________ from Account #____________ to Account #_______________

      ____ Not Budgeted - account #____________ requires budget increase of $_____________.

 

   Capital Project - **THE PRE-PROJECT CHECKLIST AND BUDGET CHECKLIST MUST BE ATTACHED TO THIS FILE**

      In current year Capital Projects Plan: 

        _____ Yes, planned amount $___________, requesting $_________ as total project estimate, including contingencies, under account #_________________

        __x__ No, requesting $15,000___________ as total project estimate, including contingencies, under account #12-600-9385 A11 GUARD__________

 

Body

 

     WHEREAS, there is a need to make safety improvements in the vicinity of the existing guardrail location along the Foley Beach Express approximately 2,000 feet north of CR 12, and

     WHEREAS, the Engineering Department has identified potential improvements in this location by relocating the existing guardrail more towards the toe of the ditch slope, and

     WHEREAS, a proposal has been solicited from C&H Construction Services, LLC for work associated with removing the existing guardrail infrastructure and installing new guardrail towards the toe of the ditch slope.

 

     NOW THEREFORE BE IT RESOLVED that the City Council of the City of Foley, Alabama, as follows:

     SECTION 1:     Appropriates $15,000.00 for the Foley Beach Express Guardrail Relocation Safety project for Account No. 12-600-9385 A11 GUARD.

     SECTION 2:     Approves C&H Construction Services, LLC’s proposal in the amount of $13,200.00 for the guardrail removal and installation service for Account No. 12-600-9385 A11 GUARD.

     SECTION 3:     This Resolution shall become effective immediately upon its adoption as required by law.