Description of Topic: (who, what, where, when, why and how much)

Repairs were done to the Peteet Building which houses Foley Art Center in 2018. The building is in need of additional repairs and we estimate that cost to be $16,000. There is rotten siding all over the building with mold now growing on the exterior. We also would like to add gutters around the building to help keep the siding from rotting and water from going under the building. We received two options from Bluewater Exteriors. We recommend Option 1. 

 

Budgetary Impact:

   Non-Capital Item:

      ____ Budgeted under account #_______________ (discussion item)

      ____ Not budgeted, requesting transfer of $__________ from Account #______________ to Account #_____________.**Request to Transfer Departmental Budget Dollars form must be attached**

      ____ Not budgeted requiring increase to account #___________ in the amount of $____________.**Request to Increase Departmental Budget Dollars form must be attached**

 

   Capital - Departmental **Capital Purchase Worksheet form must be attached**

      ____ Budgeted under account #______________ for $_________ and described in budget as ________________________. Additional amount needed, if any: Increase in budget of  $_________ OR, transfer of $________ from Account #____________ to Account #_____________**Request to Increase OR Request toTransfer Departmental Budget Dollars form must be attached**

      ____ Not Budgeted - account #____________ requires budget increase of $_____________.**Request to Increase Departmental Budget Dollars form must be attached**

 

   Capital Project - **If requesting to start a project, a Capital Project Worksheet form must be attached**

      In current year Capital Projects Plan: 

        _____ Yes, described as __________________________, planned amount $___________, requesting $_________ as total project estimate, including contingencies, under account #_________________

        __XX___ No, requesting $_20,976___ as total project estimate, including contingencies, under account #__400-3020-5130_____.

        _____ No, requesting an increase of $___________ to an already approved project titled ________________________ that is being tracked under Account No. ___________________.

 

Body

 

     WHEREAS,  The Peteet Building which houses the Foley Art Center is in need of repairs, and

 

     WHEREAS,  We received a quote from Bluewater Exteriors to install gutters around the building.

 

     NOW THEREFORE BE IT RESOLVED that the City Council of the City of Foley, Alabama, as follows:

    

     SECTION 1:  Approves the repairs to the building not to exceed $16,000.

 

     SECTION 2:  Accepts Bluewater Exterions' quote for Option 1 for gutter installation in the amount of $4,976.

 

     SECTION 3:  Appropriates $20,976 under Account No. 400-3020-5130.

     

     SECTION 4:  This Resolution shall become effective immediately upon its adoption as required by law.