File #: 19-0451    Version: 1 Name: A RESOLUTION APPROPRIATING ADDITIONAL FUNDS FOR HERITAGE PARK GAZEBO STEPS PROJECT
Type: Resolution Status: Adopted
File created: 8/22/2019 In control:
On agenda: 9/3/2019 Final action: 9/3/2019
Title: A RESOLUTION APPROPRIATING ADDITIONAL FUNDS FOR HERITAGE PARK GAZEBO STEPS PROJECT
Attachments: 1. Bid Tab - Heritage Park Gazebo Steps, 2. Handrail Addition, 3. Budget Increase Gazebo Steps

Title

A RESOLUTION APPROPRIATING ADDITIONAL FUNDS FOR HERITAGE PARK GAZEBO STEPS PROJECT

 

Summary

Description of Topic: (who, what, where, when, why and how much)

Res. 19-1186 appropriated up to $30,000 for the Gazebo Steps renovation. The lowest bid came in from EJ Builders for $34,971.25. We have decided to two new handrails in addition to the existing handrails, have handrails fabricated and installed to the new area. We estimate the cost to be $2,000. We are asking for an additional $7,000 to finish this project.

 

Budgetary Impact:

   Non-Capital Item:

      ____ Budgeted under account #_______________ (discussion item)

      ____ Not budgeted, requesting transfer of $__________ from Account #______________ to Account #_____________.**Request to Transfer Departmental Budget Dollars form must be attached**

      ____ Not budgeted requiring increase to account #___________ in the amount of $____________.**Request to Increase Departmental Budget Dollars form must be attached**

 

   Capital - Departmental **Capital Purchase Worksheet form must be attached**

      ____ Budgeted under account #______________ for $_________ and described in budget as ________________________. Additional amount needed, if any: Increase in budget of  $_________ OR, transfer of $________ from Account #____________ to Account #_____________**Request to Increase OR Request toTransfer Departmental Budget Dollars form must be attached**

      ____ Not Budgeted - account #____________ requires budget increase of $_____________.**Request to Increase Departmental Budget Dollars form must be attached**

 

   Capital Project - **If requesting to start a project, a Capital Project Worksheet form must be attached**

      In current year Capital Projects Plan: 

        __X__ Yes, planned amount $30,000, requesting additional $7,000 as total project estimate, including contingencies, under account #400-3020-5145 HPGS.

        _____ No, requesting $___________ as total project estimate, including contingencies, under account #____________________.

        _____ No, requesting an increase of $___________ to an already approved project titled ________________________ that is being tracked under Account No. ___________________.

 

Body

     WHEREAS,  Resolution 19-1186 appropriated up $30,000 for the Heritage Park Gazebo Steps Project, and

     WHEREAS,  Sealed Bids were publicly opened at 10:00 am on Tuesday, August 20, 2019, and

     WHEREAS,  E-J Builders, Inc submitted the lowest responsible bid in the amount of $34,971.25, and

     WHEREAS,  We need to replace the existing handrail and estimate the cost to be $2,000.00.

 

     NOW THEREFORE BE IT RESOLVED that the City Council of the City of Foley, Alabama, as follows:

 

     SECTION 1:  Awards the bid to E-J Builders, Inc. in the amount of $34,971.25.

     SECTION 2:  Approves adding two new fabricated handrails at the cost of $2,000.00.

     SECTION 3:  Appropriates an additional $7,000.00 under Account No. 400-3020-5145 HPGS.

     SECTION 4:  This Resolution shall become effective immediately upon its adoption as required by law.