Title
A Resolution Approving Bid Award for Juniper Street South Extension Project
Summary
Description of Topic: (who, what, where, when, why and how much)
Bids were publicly opened March 31, 2022 with McElhenney Construction being the lowest responsible bidder in the amount of $4,528,081.68. GMC recommends awarding the project to McElhenney Construction.
Budgetary Impact:
Non-Capital Item:
____ Budgeted under account #_______________ (discussion item)
____ Not budgeted, requesting transfer of $__________ from Account #______________ to Account #_____________.**Request to Transfer Departmental Budget Dollars form must be attached**
____ Not budgeted requiring increase to account #___________ in the amount of $____________.**Request to Increase Departmental Budget Dollars form must be attached**
Capital - Departmental **Capital Purchase Worksheet form must be attached**
____ Budgeted under account #______________ for $_________ and described in budget as ________________________. Additional amount needed, if any: Increase in budget of $_________ OR, transfer of $________ from Account #____________ to Account #_____________**Request to Increase OR Request toTransfer Departmental Budget Dollars form must be attached**
____ Not Budgeted - account #____________ requires budget increase of $_____________.**Request to Increase Departmental Budget Dollars form must be attached**
Capital Project - **If requesting to start a project, a Capital Project Worksheet form must be attached**
In current year Capital Projects Plan:
_____ Yes, described as __________________________, planned amount $___________, requesting $_________ as total project estimate, including contingencies, under account #_________________
_____ No, requesting $___________ as total project estimate, including contingencies, under account #____________________.
__X__ yes, requesting an increase of $4,528,081.68 to an already approved project titled Juniper St South Extension that is being tracked under Account No. 400-3020-5141 R42 CONST.
Body
WHEREAS, Sealed bids were publicly opened on March 31, 2022, and
WHEREAS, McElhenney Construction was the lowest responsible bidder in the amount of $4,528,081.68.
NOW THEREFORE BE IT RESOLVED that the City Council of the City of Foley, Alabama, as follows:
SECTION 1: Awards McElhenney Construction lowest responsible bidder for the Juniper Street South Extension Project and appropriates funds in the amount of $4,528,081.68 under Account No. 400-3020-5141 R42 CONST.
SECTION 2: This Resolution shall become effective immediately upon its adoption as required by law.