Skip to main content
Sign In
  • Home
  • Legislation
  • Calendar
  • City Council
  • Departments
  • People
Loading...
{1}
##LOC[OK]##
{1}
##LOC[OK]## ##LOC[Cancel]##
{1}
##LOC[OK]## ##LOC[Cancel]##
  • Details
  • Reports

Legislation Details

File #: 16-0020    Version: 1 Name: Change Order No. 1 for Pedestrian Bridge Project
Type: Resolution Status: Adopted
File created: 1/11/2016 In control:
On agenda: 1/19/2016 Final action: 1/19/2016
Title: Change Order No. 1 for the TIGER Phase 3 Pedestrian Bridge Project
Attachments: 1. Morette C.O. #1 Ped. Bridge
Related files: 15-0393
  • History (1)
  • Text
  • 1 record
  • Group
    • Clear sorting
    • Clear grouping
    • Group by Date
    • Group by Action By
  • Export
    • Export to Excel
    • Export to PDF
    • Export to Word
Date Ver.Action ByActionResultAction DetailsMeeting DetailsVideo
1/19/20161 City Council adoptedPass Action details Meeting details Not available

Title

Change Order No. 1 for the TIGER Phase 3 Pedestrian Bridge Project

 

Summary

Description of Topic: (who, what, where, when, why and how much)

Consider approving Change Order No. 1 for the additional right of way bond for the ALDOT permit for the TIGER Phase 3 Pedestrian Bridge project.

 

Budgetary Impact:

   Non-Capital Item:

      ____ Budgeted under account #_______________ (discussion item)

      ____ Not budgeted, requesting transfer of $__________ from Account #______________ to Account #_____________.

      ____ Not budgeted requiring increase to account #___________ in the amount of $____________.

 

   Capital - Departmental

      ____ Budgeted under account #______________ for $___________ and described in budget as __________________________________.

                    Additional amount needed, if any: Increase in budget of  $_____________ OR, transfer of $___________ from Account #____________ to Account #_______________

      ____ Not Budgeted - account #____________ requires budget increase of $_____________.

 

   Capital Project - **THE PRE-PROJECT CHECKLIST AND BUDGET CHECKLIST MUST BE ATTACHED TO THIS FILE**

      In current year Capital Projects Plan: 

        __X__ Yes, planned amount $1,515,478.15____, requesting $1,518,963.80___ as total project estimate, including contingencies, under account #31-665-7300______

        _____ No, requesting $___________ as total project estimate, including contingencies, under account #____________________

 

Body

 

     WHEREAS, Resolution No. 15-2214 approved awarding the TIGER Phase 3 project to the Morette Company in the amount of $1,515,478.15, and

 

     WHEREAS, an additional right of way bond is required for the ALDOT permit which will increase the contract amount by $3,485.65 making the new contract price $1,515,963.80.

 

     NOW THEREFORE BE IT RESOLVED that the City Council of the City of Foley, Alabama, as follows:

 

     SECTION 1:     Approves amending Account No. 31-665-7300 by an increase of $3,485.65 to Morette Company's contract price for the additional right of way bond for the TIGER Phase 3 Pedestrian Bridge project.

 

     SECTION 2:     This Resolution shall become effective immediately upon its adoption as required by law.

Legislation Text
Legislation Details
Legislation Details (With Text)