Request approval to a $250,000 increase the CE&I contract for the ATRIP Pride Drive Extension project.
Budgetary Impact:
Non-Capital Item:
____ Budgeted under account #_______________ (discussion item)
____ Not budgeted, requesting transfer of $__________ from Account #______________ to Account #_____________.
____ Not budgeted requiring increase to account #___________ in the amount of $____________.
Capital - Departmental
____ Budgeted under account #______________ for $___________ and described in budget as __________________________________.
Additional amount needed, if any: Increase in budget of $_____________ OR, transfer of $___________ from Account #____________ to Account #_______________
____ Not Budgeted - account #____________ requires budget increase of $_____________.
Capital Project - **THE PRE-PROJECT CHECKLIST AND BUDGET CHECKLIST MUST BE ATTACHED TO THIS FILE**
In current year Capital Projects Plan:
__x__ Yes, planned amount $910,604.63_____, requesting $1,160,604.63_______ as total project estimate, including contingencies, under account #12-665-7311 Q88 PROF____ ATRIP PRIDE DR. EXT.
_____ No, requesting $___________ as total project estimate, including contingencies, under account #____________________
Body
WHEREAS, the originally approved CE&I contract was amended by ALDOT, and
WHEREAS, a reduction in time of construction and CE&I resulted, and
WHEREAS, ALDOT has now approved the addition of 135 days of construction time and will pay for 80% of the increased CE&I costs as a result.
NOW THEREFORE BE IT RESOLVED that the City Council of the City of Foley, Alabama, as follows:
SECTION 1: Approves amending Volkert's CE&I contract by an increase of $250,000 for a total of $1,160,604.63, amending account no. 12-665-7311 Q88 PROF.