File #: 21-0569    Version: 1 Name: A Resolution to Accept the Bid Submitted by S.C. Stagner Contracting, Inc. in the Amount of $2,444,226.00 for the Demo and Replacement of the North Apron Hangars at the Foley Municipal Airport
Type: Resolution Status: Adopted
File created: 9/20/2021 In control:
On agenda: 10/4/2021 Final action: 10/4/2021
Title: A Resolution to Accept the Bid Submitted by S.C. Stagner Contracting, Inc. in the Amount of $2,444,226.00 for the Demo and Replacement of the North Apron Hangars at the Foley Municipal Airport
Attachments: 1. 1059404 - Bid Results and Recommendation.pdf, 2. S.C. STAGNER PROPOSAL.pdf

Title

A Resolution to Accept the Bid Submitted by S.C. Stagner Contracting, Inc. in the Amount of $2,444,226.00 for the Demo and Replacement of the North Apron Hangars at the Foley Municipal Airport

 

Summary

Description of Topic: (who, what, where, when, why and how much)

Bids were received on September 2, 2021 at 10:00 a.m. for the demo and replacement of the north apron hangars at the airport that were damaged by Hurricane Sally.  The lowest, responsible bid was submitted by S.C. Stagner for a base bid price of $2,444,226.00 and Additive Alternate 1 price of $200,500.00 to upgrade the roof from R-panel to a standing seam roof.  Insurance will cover the base bid construction cost with the exception of asphalt related items which total $88,751.00 and the cost of one fire hydrant in the amount of $5,000 for a total of $93,751. Total covered by insurance is expected to be $2,350,475.00.  I will not request the roof upgrade to keep the City cost down.

 

 

Budgetary Impact:

   Non-Capital Item:

      ____ Budgeted under account #_______________ (discussion item)

      ____ Not budgeted, requesting transfer of $__________ from Account #______________ to Account #_____________.**Request to Transfer Departmental Budget Dollars form must be attached**

      ____ Not budgeted requiring increase to account #___________ in the amount of $____________.**Request to Increase Departmental Budget Dollars form must be attached**

 

   Capital - Departmental **Capital Purchase Worksheet form must be attached**

      ____ Budgeted under account #______________ for $_________ and described in budget as ________________________. Additional amount needed, if any: Increase in budget of  $_________ OR, transfer of $________ from Account #____________ to Account #_____________**Request to Increase OR Request toTransfer Departmental Budget Dollars form must be attached**

      ____ Not Budgeted - account #____________requires budget increase of $_____________.**Request to Increase Departmental Budget Dollars form must be attached**

 

   Capital Project - **If requesting to start a project, a Capital Project Worksheet form must be attached**

      In current year Capital Projects Plan: 

        _____ Yes, described as __________________________, planned amount $___________, requesting $_________ as total project estimate, including contingencies, under account #_________________

        __X___ No, requesting $2,688,648.60 for a total project estimate, including a 10% contingency, under account #100-9200-5101 S03.1 E1.

        _____ No, requesting an increase of $___________ to an already approved project titled ________________________ that is being tracked under Account No. ___________________.

 

Body

 

     WHEREAS, bids were solicited and received on Thursday, September 2, 2021, at 10:00 a.m. for the demo and replacement of the north apron hangars at the Foley Municipal Airport which were substantially damaged by Hurricane Sally, and,

     WHEREAS, S.C. Stagner Contracting, Inc. submitted the lowest, responsible bid in the amount of $2,444,226.00 for the base bid plus $200,500.00 for Alternate 1 to upgrade the R-panel roof with a standing seam roof on all hangars, and,

     WHEREAS, AMIC insurance funds will cover the majority of the base bid cost with the exception of asphalt related line items and miscellaneous items that total approximately $100,000.00, and,

     WHEREAS, it is recommended to rebuild with an R-panel roof instead of upgrading to a standing seam roof which is not covered by insurance.

      NOW THEREFORE BE IT RESOLVED that the City Council of the City of Foley, Alabama, as follows:

     SECTION 1:     Accepts the lowest, responsible bid submitted by S.C. Stagner Contracting, Inc. for the base bid amount of $2,444,226.00.

     SECTION 2:     Appropriates $2,444,226.00 plus a 10% contingency in the amount of $244,422.60 for a total of $2,688,648.60 to account 100-9200-5101 S03.1 E1.

     SECTION 2:     This Resolution shall become effective immediately upon its adoption as required by law.