File #: 24-0084    Version: 1 Name: Resolution approving the professional services proposal from Thompson Engineering and appropriate funding for Michigan Avenue at Cedar Street and Michigan Avenue at Juniper Street.
Type: Resolution Status: Adopted
File created: 1/24/2024 In control:
On agenda: 2/5/2024 Final action: 2/5/2024
Title: Resolution Approving the Professional Services Proposal from Thompson Engineering and Appropriate Funding for Michigan Avenue at Cedar Street and Michigan Avenue at Juniper Street.
Attachments: 1. Proposal - Michigan at Cedar Roundabout, 2. Proposal - Michigan at Juniper Roundabout, 3. Budget Increase Capital Projects, 4. Capital Project Worksheet

Title

Resolution Approving the Professional Services Proposal from Thompson Engineering and Appropriate Funding for Michigan Avenue at Cedar Street and Michigan Avenue at Juniper Street.

 

Summary

Description of Topic: (who, what, where, when, why and how much) 21-1204RES approved a citywide intersection study to be performed by Thompson Engineering, 22-1120RES approved Thompson Engineering's proposal of providing 30% construction plans completion for multiple intersection improvements including Michigan Avenue/Juniper Street and Michigan Avenue/Cedar Street. We are requesting a professional services design proposal for the 100% construction plan design for the Michigan Avenue/Cedar Street intersection and the Michigan Avenue/Juniper Street intersection improvements for a roundabout design for each intersection.

 

Budgetary Impact:

   Non-Capital Item:

      ____ Budgeted under account #_______________ (discussion item)

      ____ Not budgeted, requesting transfer of $__________ from Account #______________ to Account #_____________.**Request to Transfer Departmental Budget Dollars form must be attached**

      ____ Not budgeted requiring increase to account #___________ in the amount of $____________.**Request to Increase Departmental Budget Dollars form must be attached**

 

   Capital - Departmental **Capital Purchase Worksheet form must be attached**

      ____ Budgeted under account #______________ for $_________ and described in budget as ________________________. Additional amount needed, if any: Increase in budget of  $_________ OR, transfer of $________ from Account #____________ to Account #_____________**Request to Increase OR Request toTransfer Departmental Budget Dollars form must be attached**

      _X___ Not Budgeted - account #400-3020-5161 Intersection Improvements-Michigan/Cedar $156,500.00 requires budget increase and 400-3020-5162 Intersection Improvements-Michigan/Juniper $158,500.00 requires budget increase of**Request to Increase Departmental Budget Dollars form must be attached**

 

   Capital Project - **If requesting to start a project, a Capital Project Worksheet form must be attached**

      In current year Capital Projects Plan: 

        _____ Yes, described as __________________________, planned amount $___________, requesting $_________ as total project estimate, including contingencies, under account #_________________

        _____ No, requesting $___________ as total project estimate, including contingencies, under account #____________________.

        _X____ Yes, requesting an increase of $156,500.00 for Michigan Avenue at Cedar Street and $158,500.00 for Michigan Avenue at Juniper Street to an already approved project titled Intersection Improvements-Michigan/Cedar and Intersection Improvements-Michigan/Juniper that is being tracked under Account No.400-3020-5161 and 400-3020-5162.

        _____ No, requesting an increase of $__________ to an already approved project titled _______________________ that is being tracked under Account No. _________________.

 

Body

 

     WHEREAS,  Resolution 21-1204 approved a citywide intersection study to be performed by Thompson Engineering, and

 

     WHEREAS,  Resolution 22-1120 approved Thompson Engineering's proposal of providing 30% construction plans completion for multiple intersection improvements including Michigan Avenue/Juniper Street and Michigan Avenue/Cedar Street intersections, and

 

     WHEREAS,  Engineering has requested a professional service design proposals from Thompson Engineering for the 100% construction plan design for the Michigan Avenue/Cedar Street intersection and the Michigan Avenue/Juniper Street intersection improvements for a roundabout design for each intersection, and

 

     WHEREAS,  Thompson Engineering has submitted a proposal in the amount of $156,500.00 for Michigan Avenue at Cedar Street and $158,500.00 for Michigan Avenue at Juniper Street for the 100% construction plans for said services for these two intersections which totals $315,000.00, and

 

     NOW THEREFORE BE IT RESOLVED that the City Council of the City of Foley, Alabama, as follows:

 

     SECTION 1:     Approves Thompson Engineering's professional proposal in the amount of $156,500.00 for Michigan Avenue at Cedar Street and $158,500.00 for Michigan Avenue at Juniper Street for the 100% construction plans for these two intersections and appropriates $156,500.00 to Account No# 400-3020-5161 Michigan/Cedar and $158,500.00 to Account No# 400-3020-5162 Michigan/Juniper.

 

     SECTION 2:     Authorizes the Mayor to execute Professional Services Agreements with Thompson Engineering for each of these intersections for each of these locations.

 

     SECTION 3:     This Resolution shall become effective immediately upon its adoption as required by law.