File #: 16-0355    Version: 1 Name: Transfer of Funds and Change Order for Interpretive Center
Type: Resolution Status: Adopted
File created: 6/16/2016 In control: Community Development Deptartment
On agenda: 6/20/2016 Final action: 6/20/2016
Title: Request to transfer funds between categories and approve change order #2 for Graham Creek Interpretive Center
Attachments: 1. Baldwin EMC.Transformer Quote for Graham Creek (1), 2. Budget Increase and Transfer Request Forms (1), 3. Change Order No. 002

Title

Request to transfer funds between categories and approve change order #2 for Graham Creek Interpretive Center

 

Summary

Description of Topic: (who, what, where, when, why and how much)

Request to transfer $6467.69 from the Environmental Operating Account (01-630-2010) to Capital Projects - Interpretive Center (12-665-7342 R18) for Change Order #2 for contractor purchase of Baldwin EMC transformer.

 

Budgetary Impact:

   Non-Capital Item:

      ____ Budgeted under account #_______________ (discussion item)

      ____ Not budgeted, requesting transfer of $__________ from Account #______________ to Account #_____________.

      ____ Not budgeted requiring increase to account #___________ in the amount of $____________.

 

   Capital - Departmental

      __X__ Budgeted under account #_01-630-2010 for $6467.69 and described in budget as Utilities.

                    Additional amount needed, if any: Increase in budget of  $_____________ OR, transfer of $6467.69 from Account #01-630-2010 to Account #12-665-7342 R18

      ____ Not Budgeted - account #____________ requires budget increase of $_____________.

 

   Capital Project - **THE PRE-PROJECT CHECKLIST AND BUDGET CHECKLIST MUST BE ATTACHED TO THIS FILE**

      In current year Capital Projects Plan: 

        _____ Yes, planned amount $___________, requesting $_________ as total project estimate, including contingencies, under account #_________________

        _____ No, requesting $___________ as total project estimate, including contingencies, under account #____________________

 

Body

 

     WHEREAS, the Baldwin EMC transformer at a cost of $6467.69 was not budgeted under the Capital Project - Graham Creek Interpretive Center, and

     WHEREAS, the Environmental Utilities Account had excess budgeted funds to cover the transformer, and

     WHEREAS, the Contractor has submitted a change order #2 for the purchase of the Baldwin EMC transformer in the amount of $6467.69.

     NOW THEREFORE BE IT RESOLVED that the City Council of the City of Foley, Alabama, as follows:

     SECTION 1:     Approves change order #2 for the contract with Youngblood Barrett Construction in the amount of $6467.69.  

     SECTION 2:     Approves the transfer of budget funds from the General Fund Environmental Utilities Account No. 01-630-2010 to the Capital Projects Fund Interpretive Center Account No. 12-665-7342 R18, and the necessary budget activity for the related interfund Transfer Accounts, in the amount of $6467.69.

     SECTION 3:     This Resolution shall become effective immediately upon its adoption as required by law.