Skip to main content
File #: 17-0494    Version: 1 Name: CR 20 Sidewalk Repairs Change Order No. 1
Type: Resolution Status: Adopted
File created: 8/25/2017 In control:
On agenda: 9/5/2017 Final action: 9/5/2017
Title: CR 20 Sidewalk Repairs Change Order No. 1
Attachments: 1. C.O. #1
Related files: 17-0367

Title

CR 20 Sidewalk Repairs Change Order No. 1

 

Summary

Description of Topic: (who, what, where, when, why and how much)

Request approval of Change Order No. 1 from Blade Construction in the amount of $5,297.88.00 for the CR 20 Sidewalk Repairs project.

 

Budgetary Impact:

   Non-Capital Item:

      ____ Budgeted under account #_______________ (discussion item)

      ____ Not budgeted, requesting transfer of $__________ from Account #______________ to Account #_____________.

      ____ Not budgeted requiring increase to account #___________ in the amount of $____________.

 

   Capital - Departmental

      ____ Budgeted under account #______________ for $___________ and described in budget as __________________________________.

                    Additional amount needed, if any: Increase in budget of  $_____________ OR, transfer of $___________ from Account #____________ to Account #_______________

      ____ Not Budgeted - account #____________ requires budget increase of $_____________.

 

   Capital Project - **THE PRE-PROJECT CHECKLIST AND BUDGET CHECKLIST MUST BE ATTACHED TO THIS FILE**

      In current year Capital Projects Plan: 

        __x__ Yes, planned amount $25,000_____, requesting $29,366.38_______ as total project estimate, including contingencies, under account #12-600-9380 CR20________

        _____ No, requesting $___________ as total project estimate, including contingencies, under account #____________________

 

Body

 

     WHEREAS, the Council approved Blade Construction’s proposal for the CR 20 Sidewalk Repairs on July 5, 2017 in the amount of $24,068.50 per Resolution No. 17-1178, and

 

     WHEREAS, Blade Construction has submitted a change order in the amount of $5,297.88 due to increases in plan quantities for concrete and dowels.

 

     NOW THEREFORE BE IT RESOLVED that the City Council of the City of Foley, Alabama, as follows:

 

     SECTION 1:     Approves Blade Construction’s Change Order No. 1 in the amount $5,297.88, amending Account No. 12-600-9380 CR20 and the budget accordingly.

    

     SECTION 2:     This Resolution shall become effective immediately upon its adoption as required by law.