Title: Resolution Approving Sawgrass Consulting's Professional Services Proposal for Fiscal Year 2025 Resurfacing Project
Attachments: 1. Sawgrass Prof Serv, 2. Sawgrass Preliminary FY25 Resurfacing Budget Estimate, 3. Preliminary street map, 4. Daisha-Barnes-Engineering (19)

Title

Resolution Approving Sawgrass Consulting's Professional Services Proposal for Fiscal Year 2025 Resurfacing Project

 

Summary

Description of Topic: (who, what, where, when, why and how much) Engineering received a proposal from Sawagrass Consulting for our FY2025 Resurfacing Project. $1,300,000.00 is budgeted in the FY25 Capital Plan for Resurfacing.

 

Budgetary Impact:

   Non-Capital Item:

      ____ Budgeted under account #_______________ (discussion item)

      ____ Not budgeted, requesting transfer of $__________ from Account #______________ to Account #_____________.**Request to Transfer Departmental Budget Dollars form must be attached**

      ____ Not budgeted requiring increase to account #___________ in the amount of $____________.**Request to Increase Departmental Budget Dollars form must be attached**

 

   Capital - Departmental **Capital Purchase Worksheet form must be attached**

      ____ Budgeted under account #______________ for $_________ and described in budget as ________________________. Additional amount needed, if any: Increase in budget of  $_________ OR, transfer of $________ from Account #____________ to Account #_____________**Request to Increase OR Request toTransfer Departmental Budget Dollars form must be attached**

      ____ Not Budgeted - account #____________ requires budget increase of $_____________.**Request to Increase Departmental Budget Dollars form must be attached**

 

   Capital Project - **If requesting to start a project, a Capital Project Worksheet form must be attached**

      In current year Capital Projects Plan: 

        __X___ Yes, described as Street Resurfacing & Repairs, planned amount $225,150.00, requesting $1,300,000.00 as total project estimate, including contingencies, under account #400-3020-6197 A13 FY25

        _____ No, requesting $___________ as total project estimate, including contingencies, under account #____________________.

        _____ Yes, requesting an increase of $___________ to an already approved project titled ________________________ that is being tracked under Account No. ___________________.

        _____ No, requesting an increase of $__________ to an already approved project titled _______________________ that is being tracked under Account No. _________________.

 

Body

 

     WHEREAS,  $1,300,000.00 is included in the FY25 Capital Plan for Resurfacing, and

 

     WHEREAS,  the streets recommended for the FY 25 resurfacing project are a result of each street's pavement index score and other existing conditions upon field inspection, and

 

     WHEREAS, Engineering received a professional services proposal and preliminary construction estimate from Sawgrass Consulting, and

 

     WHEREAS,  a proposal from Sawgrass Consulting has been received for the professional services in the amount of $225,150.00 based on the preliminary construction estimate.

 

     NOW THEREFORE BE IT RESOLVED that the City Council of the City of Foley, Alabama, as follows:

 

     SECTION 1:     Authorizes the Mayor to execute the Professional Services Agreement with Sawgrass Consulting in accordance with the terms of the reference proposal in the amount of $225,150.00 and appropriate funding in the amount of $1,300,000.00 to Account No 400-3020-6197 A13 FY25.

 

     SECTION 2:     This Resolution shall become effective immediately upon its adoption as required by law.