Skip to main content
File #: 15-0430    Version: Name: TIGER Phase 2 Bid Award
Type: Resolution Status: Adopted
File created: 7/9/2015 In control:
On agenda: 7/20/2015 Final action: 7/20/2015
Title: TIGER Phase 2 Bid Award

Title

TIGER Phase 2 Bid Award

 

Summary

Description of Topic: (who, what, where, when, why and how much)

Consider awarding the TIGER Phase 2 project to Ammons & Blackmon Construction in the amount of $1,437,340.50.

 

Budgetary Impact:

   Non-Capital Item:

      ____ Budgeted under account #_______________ (discussion item)

      ____ Not budgeted, requesting transfer of $__________ from Account #______________ to Account #_____________.

      ____ Not budgeted requiring increase to account #___________ in the amount of $____________.

 

   Capital - Departmental

      ____ Budgeted under account #______________ for $___________ and described in budget as __________________________________.

                    Additional amount needed, if any: Increase in budget of  $_____________ OR, transfer of $___________ from Account #____________ to Account #_______________

      ____ Not Budgeted - account #____________ requires budget increase of $_____________.

 

   Capital Project

      In current year Capital Projects Plan: 

        __X__ Yes, planned amount $2,252,835.00____, requesting $1,437,340.50 as total project estimate, including contingencies, under account #31-665-7200____

        _____ No, requesting $___________ as total project estimate, including contingencies, under account #____________________

 

Body

 

     WHEREAS, bids were received for the TIGER Phase 2 project on June 2, 2015 at 2:00 p.m., and

 

     WHEREAS, the lowest base bid received for this project was from Ammons & Blackmon Construction in the amount of $1,437,340.50, and

 

     WHEREAS, the budget in Account No. 31-665-7200 is $1,354,337.66

 

     NOW THEREFORE BE IT RESOLVED that the City Council of the City of Foley, Alabama, as follows:

 

     SECTION 1:     Approves awarding the lowest base bid in the amount of $1,437,340.50 for the TIGER Phase 2 project to Ammons & Blackmon Construction for Account No. 31-665-7200.

   

     SECTION 2:     Amends Account No. 31-665-7200 to increase the budget by $83,002.84.

     

     SECTION 3:     This Resolution shall become effective immediately upon its adoption as required by law.