CR 20 Access Management
Summary
Description of Topic: (who, what, where, when, why and how much)
Consider allocating $27,650 to develop a CR 20 Access Management Plan and approve Skipper Consulting to develop the plan.
Budgetary Impact:
Non-Capital Item:
____ Budgeted under account #_______________ (discussion item)
____ Not budgeted, requesting transfer of $__________ from Account #______________ to Account #_____________.
____ Not budgeted requiring increase to account #___________ in the amount of $____________.
Capital - Departmental
____ Budgeted under account #______________ for $___________ and described in budget as __________________________________.
Additional amount needed, if any: Increase in budget of $ __27,650____ OR,
_x__ Not Budgeted - account #01-624-3020________ requires budget transfer of $____________from Account #_______________ to Account _________
Capital Project - **THE PRE-PROJECT CHECKLIST AND BUDGET CHECKLIST MUST BE ATTACHED TO THIS FILE**
In current year Capital Projects Plan:
_____ Yes, planned amount $___________, requesting $_________ as total project estimate, including contingencies, under account #_________________
_____ No, requesting $___________ as total project estimate, including contingencies, under account #____________________
Body
WHEREAS, CR 20 between AL 59 and the Foley Beach Express has strong potential for development in the near term, and
WHEREAS, an overall access management plan is required to guide the safe and orderly development of this corridor.
NOW THEREFORE BE IT RESOLVED that the City Council of the City of Foley, Alabama, as follows:
SECTION 1: Approves allocating $27,650.00 to develop a Miflin Road (CR 20) Access Management Plan for Account No. 01-624-3020.
SECTION 2: Approves retaining Skipper Consulting to develop a Miflin Road (CR 20) Access Management Plan for a lump sum fee of $27,650.00.
SECTION 3: This Resolution shall become effective immediately upon its adoption as required by law.