Title
A Resolution to Accept the Bid Submitted by John G. Walton Construction Company in the amount of $217,400.00 to Rehabilitate the Access Taxiways on the North Apron at the Foley Municipal Airport
Summary
Description of Topic: (who, what, where, when, why and how much)
Bids were received on May 20, 2020 at 1 p.m. for the rehabilitation of the access taxiways on the north apron. John G. Walton Construction Company was the low bidder with the bid amount of $217,400.00.
Budgetary Impact:
Non-Capital Item:
____ Budgeted under account #_______________ (discussion item)
____ Not budgeted, requesting transfer of $__________ from Account #______________ to Account #_____________.**Request to Transfer Departmental Budget Dollars form must be attached**
____ Not budgeted requiring increase to account #___________ in the amount of $____________.**Request to Increase Departmental Budget Dollars form must be attached**
Capital - Departmental **Capital Purchase Worksheet form must be attached**
____ Budgeted under account #______________ for $_________ and described in budget as ________________________. Additional amount needed, if any: Increase in budget of $_________ OR, transfer of $________ from Account #____________ to Account #_____________**Request to Increase OR Request toTransfer Departmental Budget Dollars form must be attached**
____ Not Budgeted - account #____________ requires budget increase of $_____________.**Request to Increase Departmental Budget Dollars form must be attached**
Capital Project - **If requesting to start a project, a Capital Project Worksheet form must be attached**
In current year Capital Projects Plan:
__X___ Yes, described as Rehab North Apron planned amount $571,050, requesting $217,400 plus 10% contingency in the amount of $21,740 for a total of $239,140 as total construction project estimate, including contingencies, under account #_________________
_____ No, requesting $___________ as total project estimate, including contingencies, under account #____________________.
_____ No, requesting an increase of $___________ to an already approved project titled ________________________ that is being tracked under Account No. ___________________.
Body
WHEREAS, bids were received on May 20, 2020 at 1:00 p.m. for the rehabilitation of the access taxiway on the north apron at the Foley Municipal Airport, and,
WHEREAS, John G. Walton Construction Company submitted the lowest, responsible bid in the amount of $217,400.00.
NOW THEREFORE BE IT RESOLVED that the City Council of the City of Foley, Alabama, as follows:
SECTION 1: Accepts the lowest responsible bid submitted by John G. Walton Construction Company in the amount of $217,400.00.
SECTION 2: Appropriates $217,400.00 plus a 10% contingency in the amount of $21,740.00 for a total of $239,140.00 to account 400-1070-5105 R56 CONST.
SECTION 2: This Resolution shall become effective immediately upon its adoption as required by law.