File #: 17-0538    Version: 1 Name: Resurfacing Phase VII FY17-18 Project
Type: Resolution Status: Adopted
File created: 9/8/2017 In control:
On agenda: 9/18/2017 Final action: 9/18/2017
Title: Resurfacing Phase VII FY17-18 Project
Attachments: 1. Sawgrass Proposal, 2. Street Plan Council

Title

Resurfacing Phase VII FY17-18 Project

 

Summary

Description of Topic: (who, what, where, when, why and how much)

Consider approving the Street Resurfacing List and Sawgrass Consulting, LLC’s contract for professional services related to the Resurfacing Phase VII project.

 

Budgetary Impact:

   Non-Capital Item:

      ____ Budgeted under account #_______________ (discussion item)

      ____ Not budgeted, requesting transfer of $__________ from Account #______________ to Account #_____________.

      ____ Not budgeted requiring increase to account #___________ in the amount of $____________.

 

   Capital - Departmental

      ____ Budgeted under account #______________ for $___________ and described in budget as __________________________________.

                    Additional amount needed, if any: Increase in budget of  $_____________ OR, transfer of $___________ from Account #____________ to Account #_______________

      ____ Not Budgeted - account #____________ requires budget increase of $_____________.

 

   Capital Project - **THE PRE-PROJECT CHECKLIST AND BUDGET CHECKLIST MUST BE ATTACHED TO THIS FILE**

      In current year Capital Projects Plan: 

        __x__ Yes, planned amount $500,000______, requesting $34,301___ as design fees for FY17 and $49,220 for CE&I and testing for FY18, including contingencies, under account #12-600-9365 A13 PHVII__

        _____ No, requesting $___________ as total project estimate, including contingencies, under account #____________________

 

Body

 

     WHEREAS, the Engineering Department has updated the Street Resurfacing List for roadways in need of improvements, and

 

     WHEREAS, the Engineering Department was directed to negotiate a contract with Sawgrass Consulting, LLC for the design and construction inspection of the FY17-18 Resurfacing Phase VII project, and

 

     WHEREAS, Sawgrass Consulting, LLC provided their contract for professional engineering services related to the resurfacing of approximately 4.36 miles of roadway.

 

     NOW THEREFORE BE IT RESOLVED that the City Council of the City of Foley, Alabama, as follows:

 

     SECTION 1:     Approves the adoption of the Street Resurfacing List as presented.

 

     SECTION 2:     Approves Sawgrass Consulting, LLC’s professional services contract for design fees in FY17 in the amount of $34,301.00, and amending the budget for Account No. 12-600-9365 A13 PHVII.

 

     SECTION 3:     Approves Sawgrass Consulting, LLC’s professional services contract for construction inspection in FY18 in the amount of $49,220.00, and amending the budget for Account No. 12-600-9365 A13 PHVII.

 

     SECTION 4:     This Resolution shall become effective immediately upon its adoption as required by law.