File #: 24-0310    Version: 1 Name: Request Permission to Initiate the Wolf Creek Shoreline Stabilization Project and Allocate the Funds
Type: Resolution Status: Adopted
File created: 5/13/2024 In control: Community Development Deptartment
On agenda: 5/20/2024 Final action: 5/20/2024
Title: A Resolution Approving the Wolf Creek Shoreline Stabilization Capital Project
Attachments: 1. Proposal - City of Foley - Wolf Creek REV 3 (2), 2. Capital Project for Wolf Creek Shoreline.2024

Title

A Resolution Approving the Wolf Creek Shoreline Stabilization Capital Project

 

Summary

The Nature Parks Department requests council approval to allocate the funds and construct the Wolf Creek Park Shoreline Stabilization project. The project includes re-constructing the existing bulkhead area, design, permitting and construction of a pocket beach south of the fishing pier and repairing the kayak ramp. The original estimate was for $35,000. Due to enhanced damage of the bulkhead and collapse of the kayak ramp, the new quote was $70,000. This is a very specialized marine construction and design so we would like to select Martin Marine Engineering and Construction to perform the engineering, permitting and construction.

 

Budgetary Impact:

   Non-Capital Item:

      ____ Budgeted under account #_______________ (discussion item)

      ____ Not budgeted, requesting transfer of $__________ from Account #______________ to Account #_____________.**Request to Transfer Departmental Budget Dollars form must be attached**

      ____ Not budgeted requiring increase to account #___________ in the amount of $____________.**Request to Increase Departmental Budget Dollars form must be attached**

 

   Capital - Departmental **Capital Purchase Worksheet form must be attached**

      ____ Budgeted under account #______________ for $_________ and described in budget as ________________________. Additional amount needed, if any: Increase in budget of  $_________ OR, transfer of $________ from Account #____________ to Account #_____________**Request to Increase OR Request toTransfer Departmental Budget Dollars form must be attached**

      ____ Not Budgeted - account #____________ requires budget increase of $_____________.**Request to Increase Departmental Budget Dollars form must be attached**

 

   Capital Project - **If requesting to start a project, a Capital Project Worksheet form must be attached**

      In current year Capital Projects Plan: 

        __X__ Yes, described as Wolf Creek Shoreline Stabilization , planned amount $35,000, requesting $70,000 as total project estimate, including contingencies, under account #_. 400-5090-5100 Q83-IMPR Wolf Creek Park Improvements.__

        _____ No, requesting $___________ as total project estimate, including contingencies, under account #____________________.

        _____ Yes, requesting an increase of $___________ to an already approved project titled ________________________ that is being tracked under Account No. ___________________.

        _____ No, requesting an increase of $__________ to an already approved project titled _______________________ that is being tracked under Account No. _________________.

 

Body

 

     WHEREAS, the Nature Parks Department is requesting to begin the Wolf Creek Shoreline Stabilization Project, and

     WHEREAS, the capital project is in the 2024 Capital Projects Plan with a planned amount of $35,000, and

     WHEREAS, the planned estimate did not take into account the design, permitting and canoe launch repairs due to the increased erosion, and

     WHEREAS, the new estimate by Martin Marine includes design, permitting, shoreline stabilization, construction of a pocket beach (to minimize future erosion) and repair of the canoe launch for $70,000.

     NOW THEREFORE BE IT RESOLVED that the City Council of the City of Foley, Alabama, as follows:

     SECTION 1:     Approves the Wolf Creek Shoreline Stabilization Project by Martin Marine Engineering and Construction and allocates $70,000 in funds under Account No. 400-5090-5100 Q83-IMPR Wolf Creek Park Improvements.

     SECTION 2:     This Resolution shall become effective immediately upon its adoption as required by law.