File #: 22-0237    Version: 1 Name: A Resolution to Approve & Appropriate Funds for Road Building Project on North Pecan Street and Permission to go to Bid.
Type: Resolution Status: Adopted
File created: 4/21/2022 In control: City Council
On agenda: 7/5/2022 Final action: 7/5/2022
Title: A Resolution to Approve & Appropriate Funds for Road Building Project on North Pecan Street and Permission to go to Bid.
Attachments: 1. Capital Purchase - Capital Project Worksheet.xlsx - Capital Project

Title

A Resolution to Approve & Appropriate Funds for Road Building Project on North Pecan Street and Permission to go to Bid.

 

Summary

The extension of North Pecan Street from East Fern Avenue northward to Woodland Drive is estimated to cost $442,500. This is a planned City constructed road for FY23, budgeted for the amount of $316,174. The Street Department is requesting to move this project to FY22, and increase the funds by $126,326, under Account #400-3010-5100 CR-4, totaling in the amount of $442,500. Out of the road building components, Street Department plans to go to bid for the asphalt surfacing. Street Department expects six to nine months for the road to be completed.

 

 Budgetary Impact:

   Non-Capital Item:

      ____ Budgeted under account #_______________ (discussion item)

      ____ Not budgeted, requesting transfer of $__________ from Account #______________ to Account #_____________.**Request to Transfer Departmental Budget Dollars form must be attached**

      ____ Not budgeted requiring increase to account #___________ in the amount of $____________.**Request to Increase Departmental Budget Dollars form must be attached**

 

   Capital - Departmental **Capital Purchase Worksheet form must be attached**

      ____ Budgeted under account #______________ for $_________ and described in budget as ________________________. Additional amount needed, if any: Increase in budget of  $_________ OR, transfer of $________ from Account #____________ to Account #_____________**Request to Increase OR Request toTransfer Departmental Budget Dollars form must be attached**

      ____ Not Budgeted - account #____________ requires budget increase of $_____________.**Request to Increase Departmental Budget Dollars form must be attached**

 

   Capital Project - **If requesting to start a project, a Capital Project Worksheet form must be attached**

      In current year Capital Projects Plan: 

        ___X__ Yes, described as _North Pecan (CR-4)__, planned amount $_316,174  , requesting $_126,326 / ($442,500)__ as total project estimate, including contingencies, under account #_400-3010-5100 CR-4_

        _____ No, requesting $___________ as total project estimate, including contingencies, under account #____________________.

        _____ No, requesting an increase of $___________ to an already approved project titled ________________________ that is being tracked under Account No. ___________________.

 

Body

 

     WHEREAS, The extension of North Pecan Street from East Fern Avenue northward to Woodland Drive is estimated to cost $442,500, AND 

     WHEREAS, This is a planned City constructed road project for FY23, budgeted for the amount of $316,174, AND

     WHEREAS, The Street Department is requesting to move this project to FY22, and increase project by $126,326, for a total of $442,500 under Account #400-3010-5100 CR-4, AND

     WHEREAS, Out of the road building components, Street Department plans to go to bid for the asphalt surfacing, AND

     WHEREAS, Street Department expects six to nine months for the road to be completed.

 

     NOW THEREFORE BE IT RESOLVED that the City Council of the City of Foley, Alabama, as follows:

 

     SECTION 1:     Approves moving the extension of North Pecan Street from East Fern Avenue northward to Woodland Drive project from FY23 to FY22.

     SECTION 2:     Approves increasing the planned project by $126,326, for a total of $442,500 and amends account #400-3010-5100 CR-4 accordingly.

     SECTION 3:     Approves permission for Street Department to go to bid for the asphalt paving component of the road building project.

     SECTION 4:     Acknowledges that the Street Department is estimating six to nine months for the North Pecan extension to be completed.